Permit: TC-MDP-1223-01914
Permit Details
Apply Date:
01/05/2024
Applicant:
Daria Hopkins
Description:
SFR MER1301600 T21-M0073 REV1 roof covering change
Permit Reviews
Permit Number - TC-MDP-1223-01914
Permit Status: Complete
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/27/2024 | APPROVED |
05/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/17/2024 | APPROVED |
01/05/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 01/11/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1223-01914
Permit Status: Complete
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Date | Description | Comments |
---|---|---|
01/05/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
01/05/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
01/05/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
01/09/2024 | Post-Tension Inspection Report is required. | |
01/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
05/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
01/05/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
05/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
05/17/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
01/09/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1223-01914
Permite Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/08/2024 | COT - RSEL - Grounding/Bonding | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1223-01914
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/22/2024 | COT - RSPL - Rough Soil | Passed | ||
03/22/2024 | COT - RSPL - Yard Water Line | Passed | ||
04/08/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
04/08/2024 | COT - RSBU - Preslab | Passed | ||
04/24/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly secured to top plate with H2.5 clips. Plywood sheathing is properly secured to roof trusses and nailed per plans. Okay to dry-in roof. | |
04/24/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Masa clips and shear wall clips are properly nailed, base plates are shot/bolted/cut nailed down to the concrete floor. Sheathing for shear walls are properly nailed to the studs. Okay to proceed with window installation. | |
05/06/2024 | COT - RSPL - Sewer | Passed | Sewer line is connected to underground plumbing and under a water test. Okay to shade pipe and backfill trench. | |
05/24/2024 | BULD - Electrical Clearance | Passed | TEP ECO Clearance issued. | |
05/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in are complete. Okay to proceed with insulation and drywall installation. | |
05/24/2024 | COT - RSPL - Gas Pressure Test | Passed | gas lines are under 15# of air pressure with no leaks. okay to proceed. | |
06/18/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
07/26/2024 | COT - BULD - SWG Clearance | Passed | ||
08/09/2024 | COT - RSEL - Electrical Final | Passed | ||
08/09/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/09/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
08/09/2024 | COT - RSME - Mechanical Final | Passed | ||
08/09/2024 | COT - RSPL - Plumbing Final | Passed | ||
08/09/2024 | RSBU - Building Final | Passed | ||
08/09/2024 | RSBU - Building Progress | Passed | ||
09/11/2024 | ENGR Engineering Final | Passed |