Permit: TC-MDP-1222-00177
Permit Details
Apply Date:
12/19/2022
Applicant:
Celina Rodriguez
Description:
SFR BT1740-130 T22-M0015
Permit Reviews
Permit Number - TC-MDP-1222-00177
Permit Status: Complete
Permit Description: SFR BT1740-130 T22-M0015
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/30/2022 | RESIDENTIAL NEW DWELLING v.1 | 01/10/2023 | REQUIRES RESUBMIT |
01/17/2023 | RESIDENTIAL NEW DWELLING v.2 | 01/26/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1222-00177
Permit Status: Complete
Permit Description: SFR BT1740-130 T22-M0015
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
01/09/2023 | Post-Tension Inspection Report is required. |
06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
06/15/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1222-00177
Permit Description: SFR BT1740-130 T22-M0015
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/27/2023 | COT - RSPL - Rough Soil | Passed | ||
01/27/2023 | COT - RSPL - Yard Water Line | Passed | ||
01/27/2023 | COT - RSPL - Sewer | Passed | ||
02/03/2023 | COT - RSBU - Preslab | Passed | ||
02/03/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
02/03/2023 | COT - RSEL - Electrical Underground | Passed | ||
02/03/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
02/15/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/15/2023 | COT - RSBU - Roof Nailing | Passed | ||
03/09/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/09/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
04/03/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
06/21/2023 | COT - RSPL - Plumbing Final | Passed | ||
06/21/2023 | COT - RSEL - Electrical Final | Passed | ||
06/21/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
06/21/2023 | COT - RSME - Mechanical Final | Passed | ||
06/22/2023 | RSBU - Building Final | Passed |