Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
378 E CORONA RD UNIT 1
Apply Date:
01/04/2026
Applicant:
Ramon VALDEZ
Description:
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)

Permit Reviews

Permit Number - TC-MDP-1125-00729
Permit Status: Inspections complete
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Start Date Submittal Complete Date Status  
01/07/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/20/2026 REQUIRES RESUBMIT Review Details
03/03/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 03/16/2026 REQUIRES RESUBMIT Review Details
03/17/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 03/19/2026 APPROVED Review Details
07/30/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/31/2026 APPROVED Review Details
08/06/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/06/2026 APPROVED Review Details
01/30/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 02/11/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-1125-00729
Permit Status: Inspections complete
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Date Description Comments
11/17/2025 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
11/17/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
11/17/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
11/17/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1125-00729
Permite Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
04/28/2026 COT - RSPL - Sewer N/A Partial Pass 04/28/2026
Verified under test from sewer at main near street, okay to backfill with shading progress area. Partial pass pending connection to duplex HCS.
07/22/2026 COT - BULD - SWG Clearance N/A Not Applicable
07/22/2026 COT - RSPL - Gas Pressure Test N/A Not Applicable
08/05/2026 ENGR Engineering Final N/A Not Ready Site is complete. Conditions discussed with contractor are still unsatisfied.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1125-00729
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Completed Inspections - 18
Date Description Inspector Results Comments
03/27/2026 COT - RSPL - Rough Soil Passed 3.27.26
Approved
03/31/2026 COT - RSBU - Excavation/Rebar/Zoning Passed 3-31-26: excavation/reinforcement verified per plans. Okay for concrete placement.
03/31/2026 COT - RSBU - Preslab Passed 3-31-26: preslab, excavation/reinforcement verified per plans. Okay for concrete placement.
04/27/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 4-27-26: exterior clips/sheathing approved.
04/27/2026 COT - RSBU - Roof Nailing Passed 4-27-26: okay to dry-in
04/29/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 4/29/2026
Approved per plan, foamed top plate penetrations and sealed 2/0AWG cable at common firewall with sleeve.
04/30/2026 COT - RSPL - Sewer Passed 04/30/2026
Building sewer connection to HCS, holding under test with green tracer wire. Main water 3/4" PEX under test with blue tracer, will be in same trench but above sewer line. Okay to backfill with shading.
05/20/2026 BULD - Electrical Clearance Passed 5.2026
Approved for eco
07/22/2026 COT - RSBU - Interior Shear Bracing Passed
07/22/2026 COT - RSEL - Electrical Final Passed
07/22/2026 COT - RSEL - Electrical Underground Passed
07/22/2026 COT - RSEL - Outdoor Lighting Passed
07/22/2026 COT - RSME - Mechanical Final Passed
07/22/2026 COT - RSPL - Plumbing Final Passed
07/22/2026 COT - RSPL - Yard Water Line Passed
07/22/2026 RSBU - Building Progress Passed
07/22/2026 RSBU - Building Final Passed
08/10/2026 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-378 CORONA FINAL_V4.PDF DOCUMENTS VIEW