Permit: TC-MDP-1124-01275
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
7651 S BEST MATE PL
Address NEW:
7651 S BEST MATE PL
Apply Date:
11/04/2024
Applicant:
Alonzo Martinez
Description:
Blackhawk H30M Model Plan
Permit Reviews
Permit Number - TC-MDP-1124-01275
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/07/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 11/19/2024 | APPROVED |
| 01/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/23/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1124-01275
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 10/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 11/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Conditions
Permit Number - TC-MDP-1124-01275
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan
| Date | Description | Comments |
|---|---|---|
| 11/01/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 11/12/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/23/2025 | Post-Installed Anchor Inspection Report is required. | |
| 11/12/2024 | Post-Tension Inspection Report is required. | |
| 10/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 11/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 11/12/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 11/12/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1124-01275
Permit Description: Blackhawk H30M Model Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2024 | COT - RSPL - Yard Water Line | Passed | 11-21-24, underground plumbing, sewer connection, and main water line verified as per approved plans. Okay to backfill-provide shading. | |
| 11/21/2024 | COT - RSPL - Sewer | Passed | 11-21-24, underground plumbing, sewer connection, and main water line verified as per approved plans. Okay to backfill-provide shading. | |
| 11/21/2024 | COT - RSPL - Rough Soil | Passed | 11-21-24, underground plumbing, sewer connection, and main water line verified as per approved plans. Okay to backfill-provide shading. | |
| 12/02/2024 | BULD - Electrical Clearance | Passed | 12-2-24, electrical clearance approved. ECO clearance issued to TEP. | |
| 12/02/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12-2-24, excavation/rebar and setbacks verified and approved. Okay to pour concrete. | |
| 12/02/2024 | COT - RSBU - Preslab | Passed | 12-2-24, preslab, underground electric,excavation/rebar and setbacks verified and approved. Okay to pour concrete. | |
| 12/02/2024 | COT - RSEL - Electrical Underground | Passed | 12-2-24, preslab, underground electric,excavation/rebar and setbacks verified and approved. Okay to pour concrete. | |
| 12/02/2024 | COT - RSEL - Grounding/Bonding | Passed | 12-2-24, grounding/bonding verified at 6 feet apart, preslab, underground electric,excavation/rebar and setbacks verified and approved. Okay to pour concrete. | |
| 12/13/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Per plans 12/13/24 | |
| 12/13/2024 | COT - RSBU - Roof Nailing | Passed | Per plans 12/13/24 | |
| 12/31/2024 | COT - RSPL - Gas Pressure Test | Passed | Holds pressure 12/31/24 | |
| 01/02/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 1/2/25 corrections made | |
| 01/10/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed 1/10/25 ok to tape | |
| 02/24/2025 | COT - BULD - SWG Clearance | Passed | 24 FEB 25 Southwest Gas Clearance: SWG |
|
| 02/24/2025 | RSBU - Building Progress | Passed | ||
| 03/05/2025 | COT - RSEL - Electrical Final | Passed | ||
| 03/05/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/05/2025 | COT - RSME - Mechanical Final | Passed | ||
| 03/05/2025 | RSBU - Building Final | Passed | ||
| 03/05/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 03/05/2025 | COT - RSPL - Plumbing Final | Passed |