Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
06/04/2024
Applicant:
Brandon Kempel
Description:
SFR RKK35G T21-M0090

Permit Reviews

Permit Number - TC-MDP-1123-01846
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Start Date Submittal Complete Date Status  
06/04/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 06/05/2024 APPROVED Review Details
07/10/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/25/2024 APPROVED Review Details
06/14/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 06/17/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1123-01846
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Total Outstanding Activity Conditions - 5
Date Name
06/05/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/05/2024 Post-Tension Inspection Report is required.
06/05/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-1123-01846
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Date Description Comments
11/28/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/05/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01846
Permite Description: SFR RKK35G T21-M0090
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
07/31/2024 COT - RSBU - Excavation/Rebar/Zoning N/A Re-inspection required 7/31/24: interior footing missing per plans on east half of house, M.A.S.A clips must be properly attached at time of inspection.
07/31/2024 COT - RSBU - Preslab N/A Re-inspection required 7/31/24: interior footing missing per plans on east half of house, M.A.S.A clips must be properly attached at time of inspection.
07/31/2024 COT - RSEL - Grounding/Bonding N/A Partial Pass 7/31/24: partial for UFER ONLY

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01846
Permit Description: SFR RKK35G T21-M0090
Total Completed Inspections - 21
Date Description Inspector Results Comments
07/22/2024 COT - RSPL - Rough Soil Passed Underground plumbing is complete and connected to city sewer, entire system is under a 10' water test. Green tracer wire is installed from clean out to sewer connection. Okay to shade pipes and backfill trenches.
07/22/2024 COT - RSPL - Sewer Passed Underground plumbing is complete and connected to city sewer, entire system is under a 10' water test. Green tracer wire is installed from clean out to sewer connection. Okay to shade pipes and backfill trenches.
07/31/2024 COT - RSEL - Electrical Underground Passed
08/01/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 8/1/2024 corrections were made
08/01/2024 COT - RSBU - Preslab Passed 8/1/2024 corrections were made
08/01/2024 COT - RSEL - Grounding/Bonding Passed
08/20/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Corrections were made. 8/20/2024
08/20/2024 COT - RSBU - Roof Nailing Passed
08/28/2024 COT - RSPL - Yard Water Line Passed 8/28/24: Main water line is connected to meter and under street pressure. Okay to shade pipe and backfill trench.
09/13/2024 BULD - Electrical Clearance Passed ECO Clearance issued to TEP.
09/24/2024 COT - RSPL - Gas Pressure Test Passed
09/25/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
10/08/2024 COT - RSBU - Interior Shear Bracing Passed
12/13/2024 COT - BULD - SWG Clearance Passed pass: SWG clearance.
01/15/2025 COT - RSEL - Electrical Final Passed Passed final 1/15/25 CLEARANCE ECO
01/15/2025 COT - RSEL - Outdoor Lighting Passed Passed final 1/15/25
01/15/2025 COT - RSME - Mechanical Final Passed Passed final 1/15/25
01/15/2025 COT - RSPL - Plumbing Final Passed Passed final 1/15/25
01/21/2025 ENGR Engineering Final Passed CO Ready
01/15/2025 RSBU - Building Final Passed Passed final 1/15/25
01/15/2025 RSBU - Building Progress Passed Passed final 1/15/25

Documents

File Name Document Type  
K35G APPROVED TRUSS CALCS 9-29-22 - ALLIANCE TRUSS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
2_SITEPLAN_UPDATED COLOR SCHEME_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2024-06-04_V1.PDF DOCUMENTS VIEW