Permit: TC-MDP-1123-01841
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
10197 S ARNOLD RANCH CT
Address NEW:
10197 S ARNOLD RANCH CT
Apply Date:
08/14/2024
Applicant:
Description:
SFR RKK35G T21-M0090
Permit Reviews
Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/19/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/23/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/21/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 08/21/2024 | Post-Tension Inspection Report is required. |
| 08/21/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
| Date | Description | Comments |
|---|---|---|
| 11/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 08/21/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01841
Permite Description: SFR RKK35G T21-M0090
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2025 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 11 Mar 25 1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct. 2. Control box on air handler is missing cover. |
| 03/11/2025 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 11 Mar 25 1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct. 2. Control box on air handler is missing cover. |
| 03/11/2025 | RSBU - Building Final | N/A | Re-inspection required | 11 Mar 25 1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct. 2. Control box on air handler is missing cover. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01841
Permit Description: SFR RKK35G T21-M0090
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 09/20/2024 | COT - RSPL - Sewer | Passed | ||
| 09/20/2024 | COT - RSPL - Rough Soil | Passed | ||
| 09/30/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete. | |
| 09/30/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete. | |
| 09/30/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete. | |
| 10/01/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/23/2024 | COT - RSBU - Roof Nailing | Passed | Okay to proceed with M, P, AND E. | |
| 10/23/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Okay to proceed with M, P, AND E. | |
| 11/26/2024 | BULD - Electrical Clearance | Passed | 11-26-24, panel okay to be energized. | |
| 11/26/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 11-26-24, residential intermediate inspection approved. | |
| 11/26/2024 | COT - RSPL - Gas Pressure Test | Passed | 11-26-24, verified at 15 psi. | |
| 12/23/2024 | COT - RSBU - Interior Shear Bracing | Passed | 12/23/24 passed, ok to cover | |
| 02/07/2025 | COT - BULD - SWG Clearance | Passed | Passed CLEARANCE SWG 2/7/25 | |
| 03/11/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/11/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 03/11/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 03/11/2025 | RSBU - Building Progress | Passed | ||
| 03/13/2025 | COT - RSEL - Electrical Final | Passed | 13 March 25 Pass |
|
| 03/13/2025 | COT - RSME - Mechanical Final | Passed | 13 March 25 Pass |
|
| 03/13/2025 | RSBU - Building Final | Passed | 13 March 25 Pass |