Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
08/14/2024
Applicant:
Description:
SFR RKK35G T21-M0090

Permit Reviews

Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Start Date Submittal Complete Date Status  
08/19/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 08/23/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Total Outstanding Activity Conditions - 5
Date Name
08/21/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/21/2024 Post-Tension Inspection Report is required.
08/21/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-1123-01841
Permit Status: Inspections complete
Permit Description: SFR RKK35G T21-M0090
Date Description Comments
11/28/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/21/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01841
Permite Description: SFR RKK35G T21-M0090
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
03/11/2025 COT - RSEL - Electrical Final N/A Re-inspection required 11 Mar 25
1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct.
2. Control box on air handler is missing cover.
03/11/2025 COT - RSME - Mechanical Final N/A Re-inspection required 11 Mar 25
1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct.
2. Control box on air handler is missing cover.
03/11/2025 RSBU - Building Final N/A Re-inspection required 11 Mar 25
1. Refrigerant lines need to be supported in the attic, currently resting on the flex duct.
2. Control box on air handler is missing cover.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01841
Permit Description: SFR RKK35G T21-M0090
Total Completed Inspections - 21
Date Description Inspector Results Comments
09/20/2024 COT - RSPL - Yard Water Line Passed
09/20/2024 COT - RSPL - Sewer Passed
09/20/2024 COT - RSPL - Rough Soil Passed
09/30/2024 COT - RSBU - Preslab Passed Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete.
09/30/2024 COT - RSEL - Electrical Underground Passed Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete.
09/30/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, post tension cabling is evenly spaced, additional rebar reinforcement is in place per plan, Ufer ground is in place on side of garage, masa clips are evenly spaced at 32" on center, shear wall hold downs are placed per plan, all underground plumbing pipes are properly wrapped, and underground electrical outlets and conduit for kitchen island is installed. Okay to pour concrete.
10/01/2024 COT - RSEL - Grounding/Bonding Passed
10/23/2024 COT - RSBU - Roof Nailing Passed Okay to proceed with M, P, AND E.
10/23/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Okay to proceed with M, P, AND E.
11/26/2024 BULD - Electrical Clearance Passed 11-26-24, panel okay to be energized.
11/26/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 11-26-24, residential intermediate inspection approved.
11/26/2024 COT - RSPL - Gas Pressure Test Passed 11-26-24, verified at 15 psi.
12/23/2024 COT - RSBU - Interior Shear Bracing Passed 12/23/24 passed, ok to cover
02/07/2025 COT - BULD - SWG Clearance Passed Passed CLEARANCE SWG 2/7/25
03/11/2025 COT - RSEL - Outdoor Lighting Passed
03/11/2025 COT - RSPL - Plumbing Final Passed
03/11/2025 ENGR Engineering Final Passed CO Ready
03/11/2025 RSBU - Building Progress Passed
03/13/2025 COT - RSEL - Electrical Final Passed 13 March 25
Pass
03/13/2025 COT - RSME - Mechanical Final Passed 13 March 25
Pass
03/13/2025 RSBU - Building Final Passed 13 March 25
Pass

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2024-08-14_V1.PDF DOCUMENTS VIEW