Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
01/24/2024
Applicant:
Celina Rodriguez
Description:
SFR BT1465-130 T22-M0011

Permit Reviews

Permit Number - TC-MDP-1123-01828
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Start Date Submittal Complete Date Status  
01/24/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 01/29/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1123-01828
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Total Outstanding Activity Conditions - 5
Date Name
01/24/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/24/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/29/2024 Post-Tension Inspection Report is required.
01/29/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
11/22/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - TC-MDP-1123-01828
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Date Description Comments
11/21/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
11/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01828
Permit Description: SFR BT1465-130 T22-M0011
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/14/2024 COT - RSPL - Yard Water Line Passed
02/14/2024 COT - RSPL - Rough Soil Passed
02/21/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
02/21/2024 COT - RSBU - Preslab Passed
02/21/2024 COT - RSEL - Electrical Underground Passed
02/21/2024 COT - RSEL - Grounding/Bonding Passed
03/18/2024 COT - RSBU - Exterior Clips/Sheathing Passed All clips for roof and base plate are properly installed and secured. All interior shear walls are properly bolted and nailed down to concrete floor. Okay to proceed with exterior stucco application.
03/18/2024 COT - RSBU - Roof Nailing Passed All plywood sheathing for roof is properly nailed off. Okay to proceed with dry in of roof.
04/16/2024 COT - RSPL - Gas Pressure Test Passed
04/18/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/03/2024 COT - RSBU - Interior Shear Bracing Passed
07/15/2024 COT - BULD - SWG Clearance Passed SWG for meter only
07/22/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to sewer and under a water pressure test with no leaks in piping or joints. Okay to shade pipe and backfill trench.
07/24/2024 BULD - Electrical Clearance Passed Okay to energize panel. ECO Clearance issued to TEP for 4643 S. Brandywine Dr.
09/05/2024 COT - RSEL - Electrical Final Passed Construction is complete. Okay to issue Certificate of Occupancy.
09/05/2024 COT - RSEL - Outdoor Lighting Passed Construction is complete. Okay to issue Certificate of Occupancy.
09/05/2024 COT - RSME - Mechanical Final Passed Construction is complete. Okay to issue Certificate of Occupancy.
09/05/2024 COT - RSPL - Plumbing Final Passed Construction is complete. Okay to issue Certificate of Occupancy.
09/05/2024 ENGR Engineering Final Passed
09/05/2024 RSBU - Building Final Passed Construction is complete. Okay to issue Certificate of Occupancy.
09/05/2024 RSBU - Building Progress Passed Construction is complete. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 3 - LOT 33 START_V1.PDF DOCUMENTS VIEW
BTIII 33 SIC-2024-01-24_V1.PDF DOCUMENTS VIEW