Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
12/19/2023
Applicant:
Celina Rodriguez
Description:
SFR BT1465-130 T22-M0011

Permit Reviews

Permit Number - TC-MDP-1123-01823
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Start Date Submittal Complete Date Status  
12/20/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 01/08/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1123-01823
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Total Outstanding Activity Conditions - 4
Date Name
12/20/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/20/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
12/20/2023 Post-Installed Anchor Inspection Report is required.
12/21/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-1123-01823
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Date Description Comments
11/21/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01823
Permit Description: SFR BT1465-130 T22-M0011
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/08/2024 COT - RSPL - Yard Water Line Passed
02/08/2024 COT - RSPL - Sewer Passed
02/08/2024 COT - RSPL - Rough Soil Passed
02/08/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
02/08/2024 COT - RSBU - Preslab Passed
02/08/2024 COT - RSEL - Electrical Underground Passed
02/08/2024 COT - RSEL - Grounding/Bonding Passed
02/08/2024 COT - RSBU - Exterior Clips/Sheathing Passed
02/08/2024 COT - RSBU - Roof Nailing Passed
03/20/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
03/20/2024 COT - RSPL - Gas Pressure Test Passed
04/05/2024 COT - RSBU - Interior Shear Bracing Passed Drywall for interior shear wall is properly installed and secured to the studs per plan requirements. Okay to proceed with tape, texture, and painting of interior walls and ceilings.
05/02/2024 BULD - Electrical Clearance Passed
05/25/2024 COT - BULD - SWG Clearance Passed SWG for meter only
06/18/2024 COT - RSEL - Electrical Final Passed
06/18/2024 COT - RSEL - Outdoor Lighting Passed
06/18/2024 COT - RSME - Mechanical Final Passed
06/18/2024 COT - RSPL - Plumbing Final Passed
06/18/2024 ENGR Engineering Final Passed
06/18/2024 RSBU - Building Final Passed
06/18/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 2 - LOT 51 START_V1.PDF DOCUMENTS VIEW
BTII 51 SIC-2023-12-19_V1.PDF DOCUMENTS VIEW