Permit: TC-MDP-1123-01808
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
4741 E 1ST ST BLDG 1
Address NEW:
4741 E 1ST ST BLDG 1
Apply Date:
11/13/2023
Applicant:
Fernan Salazar
Description:
SDGM1184 Duplex
Permit Reviews
Permit Number - TC-MDP-1123-01808
Permit Status: Complete
Permit Description: SDGM1184 Duplex
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/17/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.2 | 11/17/2023 | REQUIRES RESUBMIT |
| 09/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/02/2024 | APPROVED |
| 01/24/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.5 | 01/24/2024 | APPROVED |
| 02/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/08/2024 | APPROVED |
| 11/13/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 11/14/2023 | REQUIRES RESUBMIT |
| 12/12/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.3 | 12/18/2023 | REQUIRES RESUBMIT |
| 12/20/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.4 | 01/08/2024 | REQUIRES RESUBMIT |
| 08/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/30/2024 | APPROVED |
| 04/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/04/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1123-01808
Permit Status: Complete
Permit Description: SDGM1184 Duplex
| Date | Description | Comments |
|---|---|---|
| 08/29/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/14/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1123-01808
Permite Description: SDGM1184 Duplex
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2024 | BULD - Electrical Clearance | N/A | Not Ready | 5/8/24: not ready |
| 05/08/2024 | COT - RSEL - Grounding/Bonding | N/A | Not Ready | 5/8/24: not ready |
| 08/28/2024 | COT - RSBU - Interior Shear Bracing | N/A | Re-inspection required | Letter has been submitted. EWS. Submit letter on company letterhead from Incensed contractor taking responsibility for the scope of work involved in this inspection. |
| 08/28/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 08/28/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 08/28/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1123-01808
Permit Description: SDGM1184 Duplex
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/01/2024 | COT - RSPL - Sewer | Passed | Underground plumbing is complete and connected to the main sewer line. System is under a 10' hydro test with no leaks. Okay to shade pipes, backfill trenches, and proceed with subsoil compaction for slab on grade. | |
| 03/01/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing is complete and connected to the main sewer line. System is under a 10' hydro test with no leaks. Okay to shade pipes, backfill trenches, and proceed with subsoil compaction for slab on grade. | |
| 03/12/2024 | COT - RSBU - Preslab | Passed | ||
| 03/12/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/01/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 04/01/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 05/08/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/08/2024 | RSBU - Building Progress | Passed | ||
| 05/08/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 05/10/2024 | BULD - Electrical Clearance | Passed | TEP eco 4741 e 1st street bldg 1 units 1101 and 1102 | |
| 05/10/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 08/28/2024 | COT - RSME - Mechanical Final | Passed | ||
| 08/28/2024 | ENGR Engineering Final | Passed | ||
| 08/28/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/28/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 08/28/2024 | COT - RSEL - Electrical Final | Passed | ||
| 09/23/2024 | RSBU - Building Final | Passed |