Permit: TC-MDP-1123-01794
Permit Details
Apply Date:
11/09/2023
Applicant:
Daria Hopkins
Description:
SFR 130.1600 T21-M0030
Permit Reviews
Permit Number - TC-MDP-1123-01794
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/15/2024 | REQUIRES RESUBMIT |
11/13/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 11/15/2023 | APPROVED |
09/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/27/2024 | APPROVED |
03/28/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/02/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1123-01794
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
Date | Description | Comments |
---|---|---|
11/13/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
11/13/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
11/09/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
09/27/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
03/14/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
11/13/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1123-01794
Permit Description: SFR 130.1600 T21-M0030
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/25/2024 | COT - RSPL - Rough Soil | Passed | ||
01/25/2024 | COT - RSPL - Sewer | Passed | ||
01/25/2024 | COT - RSPL - Yard Water Line | Passed | ||
01/31/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
01/31/2024 | COT - RSBU - Preslab | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
01/31/2024 | COT - RSEL - Electrical Underground | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
01/31/2024 | COT - RSEL - Grounding/Bonding | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
02/12/2024 | COT - RSBU - Roof Nailing | Passed | ||
02/16/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/23/2024 | BULD - Electrical Clearance | Passed | ||
03/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/06/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
03/22/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
04/24/2024 | COT - BULD - SWG Clearance | Passed | ||
05/21/2024 | ENGR Engineering Final | Passed | ||
05/28/2024 | COT - RSEL - Electrical Final | Passed | ||
05/28/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
05/28/2024 | COT - RSME - Mechanical Final | Passed | ||
05/28/2024 | COT - RSPL - Plumbing Final | Passed | ||
05/28/2024 | RSBU - Building Final | Passed | ||
05/28/2024 | RSBU - Building Progress | Passed |