Permit: TC-MDP-1123-01781
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
8941 E PANTANO BLUFF DR
Address NEW:
8941 E PANTANO BLUFF DR
Apply Date:
02/27/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2013-140 T22-M0036
Permit Reviews
Permit Number - TC-MDP-1123-01781
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/29/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 03/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1123-01781
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 02/29/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 03/09/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 03/09/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 03/09/2024 | Post-Installed Anchor Inspection Report is required. |
| 03/09/2024 | Post-Tension Inspection Report is required. |
| 03/09/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-1123-01781
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
| Date | Description | Comments |
|---|---|---|
| 11/07/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01781
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2024 | COT - RSPL - Sewer | Passed | ||
| 04/09/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 04/10/2024 | COT - RSPL - Rough Soil | Passed | ||
| 04/17/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/17/2024 | COT - RSBU - Preslab | Passed | ||
| 04/17/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 04/17/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/30/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 05/02/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/20/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/20/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 06/10/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 08/02/2024 | BULD - Electrical Clearance | Passed | TEP issued an ECO Clearance. Okay to energize panel. | |
| 08/02/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed at location for stove and water heater. Okay to install meter and connect gas line to meter. SWG Clearance sent to Southwest Gas Company. | |
| 08/19/2024 | COT - RSEL - Electrical Final | Passed | ||
| 08/19/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/19/2024 | COT - RSME - Mechanical Final | Passed | ||
| 08/19/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 08/19/2024 | ENGR Engineering Final | Passed | ||
| 08/19/2024 | RSBU - Building Progress | Passed | ||
| 08/23/2024 | RSBU - Building Final | Passed | 8/23/24: Construction debris has been removed. Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Okay to issue Certificate of Occupancy. |