Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
01/11/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2013-140 T22-M0036

Permit Reviews

Permit Number - TC-MDP-1123-01780
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Start Date Submittal Complete Date Status  
01/12/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 01/16/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1123-01780
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 6
Date Name
01/12/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/12/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/12/2024 Post-Installed Anchor Inspection Report is required.
01/12/2024 Post-Tension Inspection Report is required.
01/12/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
01/12/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-1123-01780
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Date Description Comments
11/07/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01780
Permite Description: SFR BT2013-140 T22-M0036
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/16/2024 ENGR Engineering Final N/A Not Ready verify rear yard drainage. does not appear to perform per plan.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01780
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/27/2024 COT - RSPL - Backwater Valve Passed
02/27/2024 COT - RSPL - Rough Soil Passed
02/27/2024 COT - RSPL - Yard Water Line Passed
02/27/2024 COT - RSPL - Sewer Passed
03/04/2024 COT - RSBU - Preslab Passed
03/04/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
03/04/2024 COT - RSEL - Grounding/Bonding Passed
03/04/2024 COT - RSEL - Electrical Underground Passed
04/01/2024 COT - RSBU - Exterior Clips/Sheathing Passed All bolts are properly installed, all clips for bottom plates are nailed to plate, all shear wall sheathing is properly nailed and secured to studs, and all rafters have h2.5 clips properly nailed to top plate. Okay to proceed with dry-in and stucco foam and lath application.
04/01/2024 COT - RSBU - Roof Nailing Passed Roof sheathing is properly nailed off, every rafter has a h2.5 clip holding it down to the top plate and is properly nailed. Okay to proceed with dry-in of roof.
04/29/2024 COT - RSPL - Gas Pressure Test Passed Gas line is under 10# of air pressure and holding. Okay to proceed.
05/03/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/03/2024 BULD - Electrical Clearance Passed TEP ECO
05/21/2024 COT - RSBU - Interior Shear Bracing Passed
07/03/2024 COT - BULD - SWG Clearance Passed Gas valves are installed in garage and attic for gas appliances. Okay to install meter and turn on gas
08/16/2024 COT - RSEL - Electrical Final Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/16/2024 COT - RSEL - Outdoor Lighting Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/16/2024 COT - RSME - Mechanical Final Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/16/2024 COT - RSPL - Plumbing Final Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/16/2024 RSBU - Building Final Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/16/2024 RSBU - Building Progress Passed Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Electrical panel is properly labeled with AFCI & GFCI breakers installed as required. GFCI outlets in bathrooms are fully operational. Okay to issue Certificate of Occupancy.
08/23/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 2 - LOT 23 START_V1.PDF DOCUMENTS VIEW
BTII 23 SIC-2024-01-11_V1.PDF DOCUMENTS VIEW