Permit Number - TC-MDP-1123-01742
Permit Status: Complete
Permit Description: SFR CASITA3X2 T20-M0046
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/20/2024 | APPROVED |
| 11/30/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 12/05/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-1123-01742
Permit Status: Complete
Permit Description: SFR CASITA3X2 T20-M0046
| Date | Description | Comments |
|---|---|---|
| 11/30/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/30/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 11/30/2023 | Masonry Inspection Report submittal review is required. | |
| 03/30/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 11/02/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 11/30/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 03/30/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1123-01742
Permit Description: SFR CASITA3X2 T20-M0046
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/14/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 02/14/2024 | COT - RSPL - Rough Soil | Passed | ||
| 02/14/2024 | COT - RSPL - Sewer | Passed | ||
| 02/21/2024 | COT - RSBU - Preslab | Passed | ||
| 02/21/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 02/21/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/26/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 07/01/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Bottom plates are secured to concrete floor with j-bolts, red head bolts, shot pins or masa clips. Plywood sheathing for exterior shear walls is properly secured to studs with nails per plan and code requirements. Okay to proceed with electrical, plumbing, and mechanical rough-in. | |
| 07/01/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are secured to top plate with nails and H2.5 clips. Roof sheathing is properly secured to trusses with nails. Okay to proceed with electrical, mechanical, and plumbing rough-in. | |
| 07/18/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/18/2024 | BULD - Electrical Clearance | Passed | ||
| 07/26/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 08/20/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 10/31/2024 | COT - RSME - Mechanical Final | Passed | ||
| 10/31/2024 | RSBU - Building Final | Passed | ||
| 10/31/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/31/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 10/31/2024 | RSBU - Building Progress | Passed | ||
| 10/31/2024 | COT - RSEL - Electrical Final | Passed | ||
| 11/13/2024 | ENGR Engineering Final | Passed |