Permit: TC-MDP-1123-01715
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
9750 E GRAY HAWK DR
Address NEW:
9750 E GRAY HAWK DR
Apply Date:
11/02/2023
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35D Model Plan
Permit Reviews
Permit Number - TC-MDP-1123-01715
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/14/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/14/2024 | APPROVED |
| 11/03/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 11/13/2023 | REQUIRES RESUBMIT |
| 02/06/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.2 | 02/13/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1123-01715
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/13/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-1123-01715
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
| Date | Description | Comments |
|---|---|---|
| 11/03/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/03/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 11/13/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 11/13/2023 | Post-Tension Inspection Report is required. | |
| 11/02/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 11/03/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01715
Permit Description: Casas del Cerrito H35D Model Plan
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/19/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 04/19/2024 | COT - RSPL - Rough Soil | Passed | ||
| 04/19/2024 | COT - RSPL - Sewer | Passed | ||
| 04/19/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 04/26/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, footing is properly dug, masa clips are spaced properly on top of form, shear wall clips are installed per plans, rebar reinforcement is installed per plans, and post tension cabling is evenly spaced per the plans. Okay to pour concrete for footings and slab on grade. | |
| 04/26/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, footing is properly dug, masa clips are spaced properly on top of form, shear wall clips are installed per plans, rebar reinforcement is installed per plans, and post tension cabling is evenly spaced per the plans. Okay to pour concrete for footings and slab on grade. | |
| 04/26/2024 | COT - RSEL - Electrical Underground | Passed | Electrical conduit is installed underground for kitchen island. | |
| 04/26/2024 | COT - RSEL - Grounding/Bonding | Passed | Ufer ground and ground rods are installed in the footing. | |
| 04/29/2024 | BULD - Electrical Clearance | Passed | TEP ECO CLEARANCE ISSUED. | |
| 05/13/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Bottom plates are properly secured to concrete floor with shot pins, masa clips, or a/b bolts. Shear wall straps are properly secured with nails to the exterior framed walls. Okay to proceed. | |
| 05/13/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly installed and nailed to the top plate with H2.5 clips, plywood sheathing is properly installed to trusses with nails holding it down. | |
| 05/29/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/29/2024 | RSBU - Building Progress | Passed | ||
| 05/30/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/13/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/22/2024 | COT - BULD - SWG Clearance | Passed | All gas valves are installed at gas appliance locations. SWG Clearance issued to Southwest Gas Company to install meter and turn on gas. | |
| 08/08/2024 | COT - RSEL - Electrical Final | Passed | ||
| 08/08/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/08/2024 | COT - RSME - Mechanical Final | Passed | ||
| 08/08/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 08/08/2024 | RSBU - Building Final | Passed | ||
| 08/21/2024 | ENGR Engineering Final | Passed |