Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-1024-01185
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
304 N SUNNY COVE PL
Address NEW:
304 N SUNNY COVE PL
Apply Date:
10/11/2024
Applicant:
Dana Petty
Description:
SFR MER1402190 T21-M0078
Permit Reviews
Permit Number - TC-MDP-1024-01185
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/17/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/29/2024 | APPROVED |
| 01/31/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/03/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-1024-01185
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078
| Date | Description | Comments |
|---|---|---|
| 10/21/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 10/17/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 10/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 10/21/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 10/21/2024 | Post-Tension Inspection Report is required. | |
| 10/10/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 10/10/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 10/21/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01185
Permite Description: SFR MER1402190 T21-M0078
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | Missing rsp4 clip at marked area, shop pins at marked area, add washer to bolt missing at entrance, add sister stud to damaged stud at bathroom |
| 01/07/2025 | COT - RSBU - Roof Nailing | N/A | Re-inspection required | Missing rsp4 clip at marked area, shop pins at marked area, add washer to bolt missing at entrance, add sister stud to damaged stud at bathroom |
| 04/10/2025 | RSBU - Building Progress | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01185
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2024 | COT - RSPL - Backwater Valve | Passed | 12-12-24, backwater valve, sewer connection, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 12/12/2024 | COT - RSPL - Yard Water Line | Passed | 12-12-24, backwater valve, sewer connection, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 12/12/2024 | COT - RSPL - Rough Soil | Passed | 12-12-24, backwater valve, sewer connection, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 12/12/2024 | COT - RSPL - Sewer | Passed | 12-12-24, backwater valve, sewer connection, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 12/17/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12/17/24 pass | |
| 12/17/2024 | COT - RSBU - Preslab | Passed | 12/17/24 pass | |
| 12/17/2024 | COT - RSEL - Grounding/Bonding | Passed | 12/17/24 pass | |
| 12/17/2024 | COT - RSEL - Electrical Underground | Passed | 12/17/24 pass | |
| 01/09/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 1-9-25, corrections made. Okay to continue construction. | |
| 01/09/2025 | COT - RSBU - Roof Nailing | Passed | 1-9-25, corrections made. Okay to continue construction. | |
| 02/05/2025 | BULD - Electrical Clearance | Passed | 2-5-25, panel okay to be energized. ECO clearance issued to TEP. | |
| 02/05/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 2-5-25, residential intermediate inspection approved plans. Okay to continue with construction. | |
| 02/05/2025 | COT - RSPL - Gas Pressure Test | Passed | 2-5-25, gas pressure test approved. | |
| 02/19/2025 | COT - RSBU - Interior Shear Bracing | Passed | 2/19/25: Drywall is properly secured to studs per plan requirements for an interior shear wall. Okay to proceed with tape, texture, and paint. | |
| 03/24/2025 | COT - BULD - SWG Clearance | Passed | 3-24-25, okay for SWG to install meter. Clearance issued. | |
| 04/01/2025 | COT - RSME - Mechanical Final | Passed | Passed final 4/1/25 | |
| 04/01/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 4/1/25 | |
| 04/03/2025 | COT - RSEL - Electrical Final | Passed | 4/3/25 corrections made | |
| 04/03/2025 | COT - RSEL - Outdoor Lighting | Passed | 4/3/25 corrections made | |
| 04/03/2025 | RSBU - Building Final | Passed | 4/3/25 corrections made | |
| 04/10/2025 | ENGR Engineering Final | Passed |