Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
232 N SUNNY COVE PL
Apply Date:
12/05/2024
Applicant:
Dana Petty
Description:
SFR MER1402190 T21-M0078 (Model master plan TC-MDP-0223-00502)

Permit Reviews

Permit Number - TC-MDP-1024-01181
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078 (Model master plan TC-MDP-0223-00502)
Start Date Submittal Complete Date Status  
01/30/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/31/2025 REQUIRES RESUBMIT Review Details
12/12/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 12/20/2024 APPROVED Review Details
06/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/23/2025 APPROVED Review Details
02/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/05/2025 APPROVED Review Details

Conditions

Permit Number - TC-MDP-1024-01181
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078 (Model master plan TC-MDP-0223-00502)
Date Description Comments
12/13/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/12/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
12/13/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/31/2025 Post-Installed Anchor Inspection Report is required.
12/13/2024 Post-Tension Inspection Report is required.
10/10/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
10/10/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
06/20/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1024-01181
Permit Description: SFR MER1402190 T21-M0078 (Model master plan TC-MDP-0223-00502)
Total Completed Inspections - 21
Date Description Inspector Results Comments
03/28/2025 COT - RSPL - Rough Soil Passed
03/28/2025 COT - RSPL - Sewer Passed
03/28/2025 COT - RSPL - Yard Water Line Passed
04/08/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 4/8/25 ok to pour concrete
04/08/2025 COT - RSBU - Preslab Passed Passed 4/8/25 ok to pour concrete
04/08/2025 COT - RSEL - Grounding/Bonding Passed Passed 4/8/25 ok to pour concrete
04/08/2025 COT - RSEL - Electrical Underground Passed Passed 4/8/25 ok to pour concrete
04/17/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Passed inspection 4/17/25
04/17/2025 COT - RSBU - Roof Nailing Passed Passed 4/17/25
05/05/2025 RSBU - Building Progress Passed Lath
05/05/2025 BULD - Electrical Clearance Passed ECO
05/05/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/05/2025 COT - RSPL - Gas Pressure Test Passed
05/19/2025 COT - RSBU - Interior Shear Bracing Passed Passed 5/19/25
07/03/2025 COT - BULD - SWG Clearance Passed Passed 7/3/25 CLEARANCE SWG
07/09/2025 COT - RSEL - Outdoor Lighting Passed Passed final 7/9/25
07/09/2025 COT - RSEL - Electrical Final Passed Passed final 7/9/25
07/09/2025 COT - RSME - Mechanical Final Passed Passed final 7/9/25
07/09/2025 COT - RSPL - Plumbing Final Passed Passed final 7/9/25
07/09/2025 ENGR Engineering Final Passed
07/09/2025 RSBU - Building Final Passed Passed final 7/9/25

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
242218-HOUGHTON RESERVE-LOT 158- PT-2025-06-16_V1.PDF DOCUMENTS VIEW
LOT 158 SPECIAL INSPECTION CERTIFICATE REVISED2-2025-02-04_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 158 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 158 SPECIAL INSPECTION CERTIFICATE-2024-12-05_V1.PDF DOCUMENTS VIEW