Permit: TC-MDP-1023-01703
Permit Details
Apply Date:
12/14/2023
Applicant:
Joshua Swinney
Description:
Eisenhower Model Plan La Escalera
Permit Reviews
Permit Number - TC-MDP-1023-01703
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/15/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 12/26/2023 | APPROVED |
11/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/08/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1023-01703
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
Date | Description | Comments |
---|---|---|
12/26/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
11/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
12/15/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
01/20/2023 | Post-Tension Inspection Report is required. | |
11/08/2024 | Post-Tension Inspection Report is required. | |
10/25/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
12/12/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
12/12/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
11/08/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
11/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
01/20/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
11/08/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1023-01703
Permite Description: Eisenhower Model Plan La Escalera
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | Not Applicable for this subdivision. No gas appliances in these houses. |
07/29/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | Not Applicable for this subdivision. No gas appliances in these houses. |
10/30/2024 | ENGR Engineering Final | N/A | Not Ready | missing clean out cover in driveway. and AC Condenser |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1023-01703
Permit Description: Eisenhower Model Plan La Escalera
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/11/2024 | COT - RSPL - Rough Soil | Passed | ||
04/11/2024 | COT - RSPL - Yard Water Line | Passed | ||
04/29/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is installed per plans and passed 3rd party inspection, rebar reinforcement is installed per plans, masa clips are properly spaced and secured to edge of form, shear wall clips are secured to form and in their proper location, all underground plumbing pipes are properly wrapped with foam to protect from damage, and underground electrical is properly installed for kitchen island. Okay to pour concrete for footings and slab. | |
04/29/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is installed per plans and passed 3rd party inspection, rebar reinforcement is installed per plans, masa clips are properly spaced and secured to edge of form, shear wall clips are secured to form and in their proper location, all underground plumbing pipes are properly wrapped with foam to protect from damage, and underground electrical is properly installed for kitchen island. Okay to pour concrete for footings and slab. | |
04/29/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is installed per plans and passed 3rd party inspection, rebar reinforcement is installed per plans, masa clips are properly spaced and secured to edge of form, shear wall clips are secured to form and in their proper location, all underground plumbing pipes are properly wrapped with foam to protect from damage, and underground electrical is properly installed for kitchen island. Okay to pour concrete for footings and slab. | |
04/29/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are set, post tension cabling is installed per plans and passed 3rd party inspection, rebar reinforcement is installed per plans, masa clips are properly spaced and secured to edge of form, shear wall clips are secured to form and in their proper location, all underground plumbing pipes are properly wrapped with foam to protect from damage, and underground electrical is properly installed for kitchen island. Okay to pour concrete for footings and slab. | |
06/03/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
06/03/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/29/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
08/15/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
09/17/2024 | COT - RSPL - Sewer | Passed | ||
09/17/2024 | RSBU - Building Progress | Passed | 9/17/24: 18 inches of copper top and bottom before sweat joint outside of wall main water line | |
10/02/2024 | BULD - Electrical Clearance | Passed | ECO Clearance issued for 7421 S Keller Ln. | |
10/31/2024 | COT - RSEL - Electrical Final | Passed | 10-31-24, listed items from previous inspection have been corrected. Building final final approved. | |
10/31/2024 | COT - RSEL - Outdoor Lighting | Passed | 10-31-24, listed items from previous inspection have been corrected. Building final final approved. | |
10/31/2024 | COT - RSME - Mechanical Final | Passed | 10-31-24, listed items from previous inspection have been corrected. Building final final approved. | |
10/31/2024 | COT - RSPL - Plumbing Final | Passed | 10-31-24, listed items from previous inspection have been corrected. Building final approved. | |
11/05/2024 | ENGR Engineering Final | Passed | CO Ready | |
11/05/2024 | RSBU - Building Final | Passed | 11-5-24, building final approved. |