Permit: TC-MDP-1023-01694
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6172 E CAMPOLINA TR
Address NEW:
6172 E CAMPOLINA TR
Apply Date:
10/24/2023
Applicant:
Helen Ormsby
Description:
Blackhawk H30A Model Plan
Permit Reviews
Permit Number - TC-MDP-1023-01694
Permit Status: Inspections complete
Permit Description: Blackhawk H30A Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/25/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 10/31/2023 | REQUIRES RESUBMIT |
| 12/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/12/2026 | APPROVED |
| 10/31/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.2 | 11/01/2023 | REQUIRES RESUBMIT |
| 02/29/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.3 | 03/18/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1023-01694
Permit Status: Inspections complete
Permit Description: Blackhawk H30A Model Plan
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-1023-01694
Permit Status: Inspections complete
Permit Description: Blackhawk H30A Model Plan
| Date | Description | Comments |
|---|---|---|
| 10/25/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/20/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 10/25/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 09/05/2023 | Post-Tension Inspection Report is required. | |
| 10/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/05/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01694
Permite Description: Blackhawk H30A Model Plan
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2025 | BULD - Electrical Clearance | N/A | Not Ready | 11.14.2025 Not ready. |
| 01/30/2026 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 1.30.26 Gas lines not installed for cooktop Hammer arrest or missing at dishwasher hot line Breaker at ac disco cannot be verified as max 30 or min 19.2 per unit listing |
| 01/30/2026 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 1.30.26 Gas lines not installed for cooktop Hammer arrest or missing at dishwasher hot line Breaker at ac disco cannot be verified as max 30 or min 19.2 per unit listing |
| 01/30/2026 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 1.30.26 Gas lines not installed for cooktop Hammer arrest or missing at dishwasher hot line Breaker at ac disco cannot be verified as max 30 or min 19.2 per unit listing |
| 01/30/2026 | RSBU - Building Final | N/A | Re-inspection required | 1.30.26 Gas lines not installed for cooktop Hammer arrest or missing at dishwasher hot line Breaker at ac disco cannot be verified as max 30 or min 19.2 per unit listing |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01694
Permit Description: Blackhawk H30A Model Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2025 | COT - RSPL - Rough Soil | Passed | 11.07.2025 Approved and all fixtures holding under test. Okay to backfill with shading materials. |
|
| 11/07/2025 | COT - RSPL - Sewer | Passed | 11.07.2025 Approved and under test with green tracer to HCS. Okay to backfill with shading materials. |
|
| 11/07/2025 | COT - RSPL - Yard Water Line | Passed | 11.07.2025 Approved and under test with blue tracer to meter. Okay to backfill with shading materials. |
|
| 11/14/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11.14.2025 Approved per site plan. |
|
| 11/14/2025 | COT - RSBU - Preslab | Passed | 11.14.2025 Approved per plan - okay for concrete placement. |
|
| 11/14/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 11/24/2025 | BULD - Electrical Clearance | Passed | 11.24.2025 Clearance for TEP ECO. |
|
| 11/24/2025 | COT - RSBU - Roof Nailing | Passed | 11.24.2025 Approved, added nails to loose roof panels in garage and kitchen areas. Added bracing to mechanical trusses per truss calc. |
|
| 11/24/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 11.24.2025 Approved, added anchor bolts at marked locations and added staples to garage shear wall. |
|
| 11/25/2025 | COT - RSEL - Grounding/Bonding | Passed | 11.25.2025 Secure riser. |
|
| 12/05/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 12.5.25 CORRECTIONS MADE, APPROVED |
|
| 12/05/2025 | COT - RSPL - Gas Pressure Test | Passed | 12.5.25 CORRECTIONS MADE, APPROVED |
|
| 12/10/2025 | COT - RSBU - Interior Shear Bracing | Passed | 12.10.25 APPROVED |
|
| 01/14/2026 | COT - BULD - SWG Clearance | Passed | 01/14/2026 Clearance for Southwest Gas. |
|
| 01/21/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 01/26/2026 | COT - RSEL - Outdoor Lighting | Passed | Passed 1/26/26 | |
| 01/26/2026 | RSBU - Building Progress | Passed | Passed 1/26/26 | |
| 02/11/2026 | COT - RSEL - Electrical Final | Passed | PASSED FINAL 2/11/26 | |
| 02/11/2026 | COT - RSME - Mechanical Final | Passed | PASSED FINAL 2/11/26 | |
| 02/11/2026 | COT - RSPL - Plumbing Final | Passed | PASSED FINAL 2/11/26 | |
| 02/11/2026 | RSBU - Building Final | Passed | PASSED FINAL 2/11/26 |