Blackhawk H30K Model Plan

Permit Reviews

Permit Number - TC-MDP-1023-01688
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
Start Date Submittal Complete Date Status  
10/24/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 10/31/2023 REQUIRES RESUBMIT Review Details
08/29/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/29/2025 APPROVED Review Details
01/22/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/23/2026 APPROVED Review Details
03/04/2024 RESTAMP - RESIDENTIAL v.1 03/05/2024 APPROVED Review Details
03/01/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.2 03/04/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-1023-01688
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
Date Description Comments
03/05/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
10/26/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/03/2023 Post-Tension Inspection Report is required.
10/18/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
10/18/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
09/07/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01688
Permit Description: Blackhawk H30K Model Plan
Total Completed Inspections - 21
Date Description Inspector Results Comments
12/11/2025 COT - RSPL - Rough Soil Passed 12.11.25
Approved - ok to proceed
12/11/2025 COT - RSPL - Sewer Passed 12.11.25
Approved - ok to proceed
12/11/2025 COT - RSPL - Yard Water Line Passed 12.11.25
Approved - ok to proceed
12/17/2025 BULD - Electrical Clearance Passed 12/17/2025
Clearance for TEP ECO.
12/17/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 12/17/2025
Approved per site plan.
12/17/2025 COT - RSBU - Preslab Passed 12/17/2025
Approved per plan, okay for concrete placement.
12/17/2025 COT - RSEL - Grounding/Bonding Passed 12/17/2025
Grounded to MSP.
12/17/2025 COT - RSEL - Electrical Underground Passed
12/29/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 12/29/2025
Approved.
12/29/2025 COT - RSBU - Roof Nailing Passed 12/29/2025
Approved, verified roof nails and truss calcs.
01/12/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 01/12/2026
Verified added foam at penetrations in garage and upstairs. Verified tub holding under test with no leaks. Added staple support to 12AWG and 8AWG wires in kitchen.
01/12/2026 COT - RSPL - Gas Pressure Test Passed 01/12/2026
Holding under test at 15psi.
01/20/2026 COT - RSBU - Interior Shear Bracing Passed
02/17/2026 COT - BULD - SWG Clearance Passed 2.17.26
Approved
02/23/2026 COT - RSEL - Electrical Final Passed Passed 2/23/26
02/23/2026 COT - RSEL - Outdoor Lighting Passed Passed 2/23/26
02/23/2026 COT - RSME - Mechanical Final Passed Passed 2/23/26
02/23/2026 COT - RSPL - Plumbing Final Passed Passed 2/23/26
02/23/2026 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
02/23/2026 RSBU - Building Final Passed Passed 2/23/26
02/23/2026 RSBU - Building Progress Passed Passed 2/23/26

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BHK 18 REVISED D1_V1.PDF DOCUMENTS VIEW
BHK 18 SEWER_V1.PDF DOCUMENTS VIEW
BHK 18 SIC REVISION_V1.PDF DOCUMENTS VIEW
BHK 18 REVISED D1_V1.PDF DOCUMENTS VIEW
BHK 18 SEWER_V1.PDF DOCUMENTS VIEW
BHK 18 SIC REVISION_V1.PDF DOCUMENTS VIEW