Permit: TC-MDP-1023-01688
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6179 E CAMPOLINA TR
Address NEW:
6179 E CAMPOLINA TR
Apply Date:
10/23/2023
Applicant:
Helen Ormsby
Description:
Blackhawk H30K Model Plan
Permit Reviews
Permit Number - TC-MDP-1023-01688
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/24/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 10/31/2023 | REQUIRES RESUBMIT |
| 08/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/29/2025 | APPROVED |
| 01/22/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/23/2026 | APPROVED |
| 03/04/2024 | RESTAMP - RESIDENTIAL v.1 | 03/05/2024 | APPROVED |
| 03/01/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.2 | 03/04/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1023-01688
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
| Date | Description | Comments |
|---|---|---|
| 03/05/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 10/26/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 10/03/2023 | Post-Tension Inspection Report is required. | |
| 10/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 10/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 09/07/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01688
Permit Description: Blackhawk H30K Model Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2025 | COT - RSPL - Rough Soil | Passed | 12.11.25 Approved - ok to proceed |
|
| 12/11/2025 | COT - RSPL - Sewer | Passed | 12.11.25 Approved - ok to proceed |
|
| 12/11/2025 | COT - RSPL - Yard Water Line | Passed | 12.11.25 Approved - ok to proceed |
|
| 12/17/2025 | BULD - Electrical Clearance | Passed | 12/17/2025 Clearance for TEP ECO. |
|
| 12/17/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12/17/2025 Approved per site plan. |
|
| 12/17/2025 | COT - RSBU - Preslab | Passed | 12/17/2025 Approved per plan, okay for concrete placement. |
|
| 12/17/2025 | COT - RSEL - Grounding/Bonding | Passed | 12/17/2025 Grounded to MSP. |
|
| 12/17/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 12/29/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 12/29/2025 Approved. |
|
| 12/29/2025 | COT - RSBU - Roof Nailing | Passed | 12/29/2025 Approved, verified roof nails and truss calcs. |
|
| 01/12/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 01/12/2026 Verified added foam at penetrations in garage and upstairs. Verified tub holding under test with no leaks. Added staple support to 12AWG and 8AWG wires in kitchen. |
|
| 01/12/2026 | COT - RSPL - Gas Pressure Test | Passed | 01/12/2026 Holding under test at 15psi. |
|
| 01/20/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 02/17/2026 | COT - BULD - SWG Clearance | Passed | 2.17.26 Approved |
|
| 02/23/2026 | COT - RSEL - Electrical Final | Passed | Passed 2/23/26 | |
| 02/23/2026 | COT - RSEL - Outdoor Lighting | Passed | Passed 2/23/26 | |
| 02/23/2026 | COT - RSME - Mechanical Final | Passed | Passed 2/23/26 | |
| 02/23/2026 | COT - RSPL - Plumbing Final | Passed | Passed 2/23/26 | |
| 02/23/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 02/23/2026 | RSBU - Building Final | Passed | Passed 2/23/26 | |
| 02/23/2026 | RSBU - Building Progress | Passed | Passed 2/23/26 |