Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
19 E ELM ST
Address NEW:
19 E ELM ST
Apply Date:
11/06/2023
Applicant:
Luis Lamadrid
Description:
SCC Plan 1368

Permit Reviews

Permit Number - TC-MDP-1023-01665
Permit Status: Complete
Permit Description: SCC Plan 1368
Start Date Submittal Complete Date Status  
04/12/2024 SITE FROM MODEL PERMIT - PRODUCTION v.6 04/12/2024 REQUIRES RESUBMIT Review Details
11/17/2023 SITE FROM MODEL PERMIT - PRODUCTION v.2 01/02/2024 REQUIRES RESUBMIT Review Details
07/10/2024 SITE FROM MODEL PERMIT - PRODUCTION v.9 07/23/2024 REQUIRES RESUBMIT Review Details
08/12/2024 RESTAMP - RESIDENTIAL v.1 08/20/2024 APPROVED Review Details
01/05/2024 SITE FROM MODEL PERMIT - PRODUCTION v.3 01/05/2024 REQUIRES RESUBMIT Review Details
05/03/2024 SITE FROM MODEL PERMIT - PRODUCTION v.8 05/14/2024 REQUIRES RESUBMIT Review Details
02/07/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/26/2025 APPROVED Review Details
01/09/2024 SITE FROM MODEL PERMIT - PRODUCTION v.4 01/17/2024 REQUIRES RESUBMIT Review Details
04/15/2024 SITE FROM MODEL PERMIT - PRODUCTION v.7 05/01/2024 REQUIRES RESUBMIT Review Details
09/24/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/24/2024 APPROVED Review Details
08/01/2024 SITE FROM MODEL PERMIT - PRODUCTION v.10 08/12/2024 APPROVED Review Details
02/29/2024 SITE FROM MODEL PERMIT - PRODUCTION v.5 04/05/2024 REQUIRES RESUBMIT Review Details
11/07/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 11/16/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-1023-01665
Permit Status: Complete
Permit Description: SCC Plan 1368
Date Description Comments
04/18/2024 Provide elevation measurements for Next Upstream Manhole and Finished Floor Elevation. Provide Backwater valve protection as/if required.
08/22/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
10/11/2023 Please submit Sewer Receipt. Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
11/07/2023 Please submit Sewer Receipt. Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/18/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
10/11/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-1023-01665
Permite Description: SCC Plan 1368
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
09/09/2024 COT - RSPL - Rough Soil N/A Re-inspection required 9/9/24: properly test system by releasing air. Properly support all piping throughout, shading required throughout. Fittings must be listed and approved for such use.
09/09/2024 COT - RSPL - Backwater Valve N/A Re-inspection required 9/9/24: properly test system by releasing air. Properly support all piping throughout, shading required throughout. Fittings must be listed and approved for such use.
09/23/2024 COT - RSBU - Interior Shear Bracing N/A Partial Pass Interior framing in place but opposite of approved plans. Contractor to,make corrections with COT.
01/22/2025 COT - BULD - SWG Clearance N/A Not Applicable Site does not use gas
01/22/2025 COT - RSEL - Electrical Underground N/A Not Applicable no underground electric
01/22/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable Site does not use gas

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1023-01665
Permit Description: SCC Plan 1368
Total Completed Inspections - 19
Date Description Inspector Results Comments
09/10/2024 COT - RSPL - Rough Soil Passed 9/9/24: properly test system by releasing air. Properly support all piping throughout, shading required throughout. Fittings must be listed and approved for such use.
9/10/24: corrections made ok to proceed. Shading required
09/10/2024 COT - RSPL - Backwater Valve Passed 9/9/24: properly test system by releasing air. Properly support all piping throughout, shading required throughout. Fittings must be listed and approved for such use.
9/10/24: corrections made ok to proceed. Shading required
09/12/2024 COT - RSBU - Preslab and floodplain Passed Slab inspection complete: ensure slab area is properly termite treated. No floodplain inspection at this time.
09/12/2024 COT - RSBU - Excavation/Rebar/Zoning Passed OK to place concrete in progress areas.
09/12/2024 COT - RSEL - Grounding/Bonding Passed Rebar ufer in place.
09/12/2024 COT - RSPL - Yard Water Line Passed
09/23/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed OK to cover exterior walls.
09/23/2024 COT - RSBU - Roof Nailing Passed OK to dry-in room system.
10/18/2024 BULD - Electrical Clearance Passed units 1 & 2
10/22/2024 COT - RSBU - Interior Shear Bracing Passed OK to insulate and cover walls.
10/22/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed OK to insulate and cover walls.
01/22/2025 COT - RSEL - Outdoor Lighting Passed Passed 1/22/25
01/22/2025 COT - RSPL - Sewer Passed Passed 1/22/25 ok to backfill
01/22/2025 RSBU - Building Progress Passed Passed 1/22/25
02/18/2025 COT - RSEL - Electrical Final Passed
02/18/2025 COT - RSME - Mechanical Final Passed
02/18/2025 COT - RSPL - Plumbing Final Passed
02/18/2025 ENGR Engineering Final Passed
02/18/2025 RSBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
TRASOS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
DECISION.PDF SPECIAL APPLICATIONS VIEW
DDO NOTICE AND MAP.PDF SPECIAL APPLICATIONS VIEW
DDO APPLICATION AND PLANS.PDF SPECIAL APPLICATIONS VIEW