Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
1184 E LIGGINS ST
Apply Date:
09/16/2025
Applicant:
Mark Alteri
Description:
PV 1520 SFR (Model master plan TC-MDP-0124-00024) Rev. 1

Permit Reviews

Permit Number - TC-MDP-0925-00544
Permit Status: Complete
Permit Description: PV 1520 SFR (Model master plan TC-MDP-0124-00024) Rev. 1
Start Date Submittal Complete Date Status  
11/17/2025 RESTAMP - RESIDENTIAL v.1 11/18/2025 APPROVED Review Details
11/10/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.4 11/17/2025 APPROVED Review Details
01/29/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/29/2026 APPROVED Review Details
09/16/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 09/23/2025 REQUIRES RESUBMIT Review Details
09/24/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.2 10/14/2025 REQUIRES RESUBMIT Review Details
10/16/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.3 11/04/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-0925-00544
Permit Status: Complete
Permit Description: PV 1520 SFR (Model master plan TC-MDP-0124-00024) Rev. 1
Date Description Comments
09/17/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
09/17/2025 Post-Tension Inspection Report is required.
09/12/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
09/12/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0925-00544
Permite Description: PV 1520 SFR (Model master plan TC-MDP-0124-00024) Rev. 1
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
12/29/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 12/29/25: DAMAGED TRUSS AT A1 and C1 at south end of home.
12/29/2025 COT - RSBU - Roof Nailing N/A Re-inspection required 12/29/25: DAMAGED TRUSS AT A1 and C1 at south end of home.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0925-00544
Permit Description: PV 1520 SFR (Model master plan TC-MDP-0124-00024) Rev. 1
Total Completed Inspections - 20
Date Description Inspector Results Comments
11/19/2025 COT - RSPL - Sewer Passed 11.19.2025
Approved. Holding under test to HCS with green tracer wire - ok to backfill with shading materials.
11/19/2025 COT - RSPL - Rough Soil Passed 11.19.2025
Approved. All fixtures according to plan holding under test - ok to backfill with shading materials.
11/19/2025 COT - RSPL - Yard Water Line Passed 11.19.2025
Approved. Holding under test to meter with blue tracer wire - ok to backfill with shading materials.
12/02/2025 COT - RSBU - Preslab Passed Ensure slab area is termite treated.
12/02/2025 COT - RSEL - Electrical Underground Passed
12/02/2025 COT - RSBU - Excavation/Rebar/Zoning Passed
01/09/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 01/09/2026
Approved. Received engineer letter, verified fix to trusses.
01/09/2026 COT - RSBU - Roof Nailing Passed 01/09/2026
Approved. Received engineer letter, verified fix to trusses.
01/27/2026 BULD - Electrical Clearance Passed 1/27/26: ECO TEP CLEARANCE APPROVED FOR 1184 E LIGGINS ST
02/11/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 2.11.26
Approved, proceed
02/11/2026 COT - RSPL - Gas Pressure Test Passed 2.11.26
Approved, proceed
02/20/2026 COT - RSBU - Interior Shear Bracing Passed Passed 2/20/26
02/20/2026 RSBU - Building Progress Passed Passed 2/20/26
04/14/2026 COT - BULD - SWG Clearance Passed 04/14/2026
Clearance for Southwest Gas.
05/19/2026 RSBU - Building Final Passed
05/19/2026 COT - RSPL - Plumbing Final Passed
05/19/2026 COT - RSME - Mechanical Final Passed
05/19/2026 COT - RSEL - Outdoor Lighting Passed
05/19/2026 COT - RSEL - Electrical Final Passed
06/05/2026 ENGR Engineering Final Passed 6/5/26 - Site is complete in accordance with approved plans.