Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
6175 E CAMPOLINA TR
Apply Date:
09/26/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30A Model Plan (Model master plan TC-MDP-0823-01432)

Permit Reviews

Permit Number - TC-MDP-0924-01133
Permit Status: Inspections complete
Permit Description: Blackhawk H30A Model Plan (Model master plan TC-MDP-0823-01432)
Start Date Submittal Complete Date Status  
08/29/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/29/2025 APPROVED Review Details
02/20/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/24/2026 APPROVED Review Details
09/27/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 10/02/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0924-01133
Permit Status: Inspections complete
Permit Description: Blackhawk H30A Model Plan (Model master plan TC-MDP-0823-01432)
Date Description Comments
10/01/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/01/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/26/2024 Post-Tension Inspection Report is required.
10/18/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
09/26/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
10/18/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
09/26/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
10/01/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
10/01/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01133
Permit Description: Blackhawk H30A Model Plan (Model master plan TC-MDP-0823-01432)
Total Completed Inspections - 21
Date Description Inspector Results Comments
12/18/2025 COT - RSPL - Rough Soil Passed 12/18/2025
Approved and all fixtures holding under test. Okay to backfill with shadings materials.
12/18/2025 COT - RSPL - Sewer Passed 12/18/2025
Approved and holding under test to HCS with green tracer. Okay to backfill with shadings materials.
12/18/2025 COT - RSPL - Yard Water Line Passed 12/18/2025
Approved and holding under test to meter with blue tracer. Okay to backfill with shadings materials.
12/24/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 12/24/2025
Approved, verified setbacks.
12/24/2025 COT - RSBU - Preslab Passed 12/24/2025
Approved per plan. Okay for concrete placement.
12/24/2025 COT - RSEL - Electrical Underground Passed
12/24/2025 BULD - Electrical Clearance Passed 12/24/2025
Clearance to TEP ECO.
12/24/2025 COT - RSEL - Grounding/Bonding Passed 12/24/2025
Tied into MSP from two ground rods.
01/21/2026 COT - RSBU - Roof Nailing Passed
01/22/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 1.22.26
Corrections made, approved
01/29/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 1/29/26 passed
01/29/2026 COT - RSPL - Gas Pressure Test Passed 1/29/26 passed
02/06/2026 COT - RSBU - Interior Shear Bracing Passed 2.6.26
Approved
03/05/2026 COT - BULD - SWG Clearance Passed 03/05/2026
Approved clearance for Southwest Gas.
03/19/2026 COT - RSEL - Electrical Final Passed
03/19/2026 COT - RSEL - Outdoor Lighting Passed
03/19/2026 COT - RSME - Mechanical Final Passed
03/19/2026 COT - RSPL - Plumbing Final Passed
03/19/2026 ENGR Engineering Final Passed
03/19/2026 RSBU - Building Final Passed
03/19/2026 RSBU - Building Progress Passed

Documents

File Name Document Type  
BHK 19 SIC-2026-02-17_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BHK 19 SIC-2024-09-26_V1.PDF DOCUMENTS VIEW
CONS-BHK 19 D1_V1.PDF DOCUMENTS VIEW