Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9823 E GRAY HAWK DR
Apply Date:
09/26/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35G Model Plan

Permit Reviews

Permit Number - TC-MDP-0924-01126
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Start Date Submittal Complete Date Status  
03/06/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/10/2025 APPROVED Review Details
09/26/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 10/02/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0924-01126
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Total Outstanding Activity Conditions - 1
Date Name
09/26/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Conditions

Permit Number - TC-MDP-0924-01126
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Date Description Comments
10/02/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
09/27/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
09/27/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/26/2024 Post-Tension Inspection Report is required.
09/26/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
09/27/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
09/27/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01126
Permit Description: Casas del Cerrito H35G Model Plan
Total Completed Inspections - 22
Date Description Inspector Results Comments
01/10/2025 COT - RSPL - Backwater Valve Passed Piping per plan and holds pressure, ok to backfill 1/10/25
01/10/2025 COT - RSPL - Rough Soil Passed Piping per plan and holds pressure, ok to backfill 1/10/25
01/10/2025 COT - RSPL - Sewer Passed
01/10/2025 COT - RSPL - Yard Water Line Passed Piping per plan and holds pressure, ok to backfill 1/10/25
01/10/2025 BULD - Electrical Clearance Passed Ready for temp power CLEARANCE ECO 1/10/25
01/17/2025 COT - RSBU - Preslab Passed Concrete forms are set into place, masa clips and shear wall hold downs are nailed to form per plan requirements, post tension cabling is evenly spaced and properly secured to forms,underground plumbing pipes are properly wrapped with foam, underground electrical for kitchen island is installed per plan requirements, Ufer ground and 2 ground rods are installed in footing with a #4 bare copper wire connected to ground rods. Okay to pour concrete for footings and slab.
01/17/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set into place, masa clips and shear wall hold downs are nailed to form per plan requirements, post tension cabling is evenly spaced and properly secured to forms,underground plumbing pipes are properly wrapped with foam, underground electrical for kitchen island is installed per plan requirements, Ufer ground and 2 ground rods are installed in footing with a #4 bare copper wire connected to ground rods. Okay to pour concrete for footings and slab.
01/17/2025 COT - RSEL - Electrical Underground Passed Concrete forms are set into place, masa clips and shear wall hold downs are nailed to form per plan requirements, post tension cabling is evenly spaced and properly secured to forms,underground plumbing pipes are properly wrapped with foam, underground electrical for kitchen island is installed per plan requirements, Ufer ground and 2 ground rods are installed in footing with a #4 bare copper wire connected to ground rods. Okay to pour concrete for footings and slab.
01/28/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 1/28/25 pass
01/28/2025 COT - RSBU - Roof Nailing Passed 1/28/25 pass
01/28/2025 COT - RSEL - Grounding/Bonding Passed 1/28/25
02/13/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 2-13-25, residential intermediate inspection approved. Okay to continue with construction.
02/13/2025 COT - RSPL - Gas Pressure Test Passed 2-13-25, gas pressure test approved
02/21/2025 COT - RSBU - Interior Shear Bracing Passed Drywall for interior shear walls is properly attached to the studs per plan requirements for an interior shear wall. Okay to proceed with tape, texture, and paint.
04/07/2025 COT - BULD - SWG Clearance Passed Passed CLEARANCE SWG 4/7/25
04/15/2025 COT - RSEL - Electrical Final Passed 4-15-25, outdoor lighting, mechanical, and electrical inspections approved.
04/15/2025 COT - RSEL - Outdoor Lighting Passed 4-15-25, outdoor lighting, mechanical, and electrical inspections approved.
04/15/2025 COT - RSME - Mechanical Final Passed 4-15-25, outdoor lighting, mechanical, and electrical inspections approved.
04/15/2025 RSBU - Building Progress Passed
04/16/2025 ENGR Engineering Final Passed There is an unconnected bare blue wire sticking out of irrigation system/ hose bib junction at SE corner of house
04/16/2025 COT - RSPL - Plumbing Final Passed Passed final 4/16/25
04/16/2025 RSBU - Building Final Passed Passed final 4/16/25

Documents

File Name Document Type  
CDC 18 SIC-2025-03-05_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 18 SIC-2024-09-26_V1.PDF DOCUMENTS VIEW
CONS-CDC 18 D1_V1.PDF DOCUMENTS VIEW