Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0924-01038
Permit Details
Apply Date:
10/08/2024
Applicant:
Daria Hopkins
Description:
SFR MER1402190 T21-M0078
Permit Reviews
Permit Number - TC-MDP-0924-01038
Permit Status: Inspections
Permit Description: SFR MER1402190 T21-M0078
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/10/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0924-01038
Permit Status: Inspections
Permit Description: SFR MER1402190 T21-M0078
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
09/19/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
10/11/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
10/11/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
10/11/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
10/11/2024 | Post-Tension Inspection Report is required. |
Conditions
Permit Number - TC-MDP-0924-01038
Permit Status: Inspections
Permit Description: SFR MER1402190 T21-M0078
Date | Description | Comments |
---|---|---|
10/10/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
09/19/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
10/11/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0924-01038
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/04/2024 | COT - RSPL - Backwater Valve | Passed | Underground plumbing is complete, double clean out is installed with backwater valve in place, all piping is connected to main sewer line with green tracer wire in place and entire system is under a water pressure test. Okay to shade pipes and backfill trenches. | |
12/04/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing is complete, double clean out is installed with backwater valve in place, all piping is connected to main sewer line with green tracer wire in place and entire system is under a water pressure test. Okay to shade pipes and backfill trenches. | |
12/04/2024 | COT - RSPL - Sewer | Passed | Underground plumbing is complete, double clean out is installed with backwater valve in place, all piping is connected to main sewer line with green tracer wire in place and entire system is under a water pressure test. Okay to shade pipes and backfill trenches. | |
12/04/2024 | COT - RSPL - Yard Water Line | Passed | Main water supply line is connected at street to main city meter and under street pressure with no leaks. Okay to shade pipe and backfill trench. | |
12/11/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12-11-24, setbacks,electrical underground, bonding/grounding, preslab per approved plans. Okay to pour concrete. | |
12/11/2024 | COT - RSBU - Preslab | Passed | 12-11-24, setbacks,electrical underground, bonding/grounding, preslab per approved plans. Okay to pour concrete. | |
12/11/2024 | COT - RSEL - Grounding/Bonding | Passed | 12-11-24, electrical underground, bonding/grounding, preslab per approved plans. Okay to pour concrete. | |
12/11/2024 | COT - RSEL - Electrical Underground | Passed | 12-11-24, electrical underground, bonding/grounding, preslab per approved plans. Okay to pour concrete. |