Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0924-01031
Permit Details
Apply Date:
09/05/2024
Applicant:
Jose Quintero
Description:
SWDUPLEXM SUNSET MODEL DUPLEX 3-2 MODEL T20-00004
Permit Reviews
Permit Number - TC-MDP-0924-01031
Permit Status: Complete
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2
MODEL T20-00004
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/04/2025 | RESTAMP - RESIDENTIAL v.1 | 04/07/2025 | APPROVED |
| 02/19/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 03/13/2025 | REQUIRES RESUBMIT |
| 03/17/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 03/28/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0924-01031
Permit Status: Complete
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2
MODEL T20-00004
| Date | Description | Comments |
|---|---|---|
| 02/19/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 09/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/20/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0924-01031
Permite Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2
MODEL T20-00004
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2025 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 7.15.25 Called twice, no answer. Cannot access site |
| 07/15/2025 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 7.15.25 Called twice, no answer. Cannot access site |
| 07/15/2025 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 7.15.25 Called twice, no answer. Cannot access site |
| 07/15/2025 | RSBU - Building Final | N/A | Re-inspection required | 7.15.25 Called twice, no answer. Cannot access site |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0924-01031
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2
MODEL T20-00004
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2025 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 4/17/2025 | |
| 04/22/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/22/2025 | COT - RSBU - Preslab | Passed | Ensure slab area is termite treated. | |
| 04/22/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/28/2025 | COT - RSPL - Sewer | Passed | Ok to cover progress area. | |
| 05/01/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 05/01/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/01/2025 | COT - RSBU - Interior Shear Bracing | Passed | Fire rated wall approved. 5/1/2025 | |
| 05/06/2025 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 05/06/2025 | BULD - Electrical Clearance | Passed | This duplex has two addresses on the permit: 1224 N. 13th Street is the West half of the building; 1224 N. Acura is the East half of the duplex. Ok to set meters for both addresses and begin new service. COCE: ECO. | |
| 05/06/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 05/06/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/04/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 07/09/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/15/2025 | ENGR Engineering Final | Passed |