Permit: TC-MDP-0924-01014
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12766 E MEAGAN RIDGE PL
Address NEW:
12766 E MEAGAN RIDGE PL
Apply Date:
09/17/2024
Applicant:
Andrea Flood
Description:
SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Permit Reviews
Permit Number - TC-MDP-0924-01014
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/20/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 09/25/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0924-01014
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 09/13/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 09/24/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 09/24/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 09/24/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 09/24/2024 | Post-Tension Inspection Report is required. |
| 09/24/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0924-01014
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
| Date | Description | Comments |
|---|---|---|
| 09/13/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/24/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01014
Permite Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2024 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | Partial pass for Ufer ground. Okay to pour concrete. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01014
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/25/2024 | COT - RSPL - Rough Soil | Passed | 10-25-24, underground plumbing inspection approved. Okay to backfill. | |
| 10/25/2024 | COT - RSPL - Sewer | Passed | 10-25-24, sewer line connection inspection approved. Okay to backfill. | |
| 10/25/2024 | COT - RSPL - Yard Water Line | Passed | 10-25-24, main water line inspection approved. Okay to backfill. | |
| 11/06/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Okay to pour concrete. | |
| 11/06/2024 | COT - RSBU - Preslab | Passed | Okay to pour concrete. | |
| 11/06/2024 | COT - RSEL - Electrical Underground | Passed | Okay to pour concrete. | |
| 12/03/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 12-3-24, exterior clip/sheathing, truss bracing and roof nailing approved. Okay to continue with construction. | |
| 12/03/2024 | COT - RSBU - Roof Nailing | Passed | 12-3-24, exterior clip/sheathing, truss bracing and roof nailing approved. Okay to continue with construction. | |
| 01/06/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 1/6/25 passed ok to proceed | |
| 01/06/2025 | COT - RSEL - Grounding/Bonding | Passed | 1/6/25 passed ok to proceed | |
| 01/06/2025 | COT - RSPL - Gas Pressure Test | Passed | Holds pressure 1/6/25 | |
| 01/10/2025 | BULD - Electrical Clearance | Passed | Ready for temp power CLEARANCE ECO | |
| 01/21/2025 | COT - RSBU - Interior Shear Bracing | Passed | 1-21-25, approved. Okay for tape & texture | |
| 03/11/2025 | COT - BULD - SWG Clearance | Passed | 11 Mar 25 Southwest gas Clearance: SWG |
|
| 03/20/2025 | COT - RSEL - Outdoor Lighting | Passed | 3-20-25, approved | |
| 03/20/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 03/20/2025 | RSBU - Building Progress | Passed | ||
| 03/21/2025 | COT - RSEL - Electrical Final | Passed | 3/21/25 passed final CLEARANCE ECO | |
| 03/21/2025 | COT - RSME - Mechanical Final | Passed | 3/21/25 passed final | |
| 03/21/2025 | COT - RSPL - Plumbing Final | Passed | 3/21/25 passed final | |
| 03/21/2025 | RSBU - Building Final | Passed | 3/21/25 passed final |