Permit: TC-MDP-0923-01586
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
7619 S PASEO DEL FADO
Address NEW:
7619 S PASEO DEL FADO
Apply Date:
12/19/2023
Applicant:
Christi Swenson
Description:
SFR PULT3515-3 T21-M0047
Permit Reviews
Permit Number - TC-MDP-0923-01586
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/19/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 12/26/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0923-01586
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 12/19/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 12/19/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 12/19/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 12/21/2023 | Post-Tension Inspection Report is required. |
| 12/21/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0923-01586
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
| Date | Description | Comments |
|---|---|---|
| 09/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01586
Permite Description: SFR PULT3515-3 T21-M0047
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/31/2024 | COT - RSPL - Sewer | N/A | Re-inspection required | 1/31/24: Cancelled, plumbing contractor has made the connection and then backfilled trench before it could be inspected. Need to expose connection and call for a re-inspection. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01586
Permit Description: SFR PULT3515-3 T21-M0047
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/25/2024 | COT - RSPL - Rough Soil | Passed | ||
| 01/25/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 01/31/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
| 01/31/2024 | COT - RSBU - Preslab | Passed | Forms are set, post tension cabling is installed per structural plan, Ufer ground is in place at meter/panel location, and all Simpson base plate clips are installed onto forms. Okay to pour concrete for footings and slab on grade. | |
| 02/02/2024 | BULD - Electrical Clearance | Passed | ||
| 02/16/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 02/16/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 02/20/2024 | COT - RSPL - Sewer | Passed | ||
| 03/26/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 04/03/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 04/03/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/08/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/10/2024 | COT - BULD - SWG Clearance | Passed | Meter is in place. 7/10/2024 | |
| 07/10/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 07/10/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/10/2024 | COT - RSME - Mechanical Final | Passed | ||
| 07/10/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 07/10/2024 | ENGR Engineering Final | Passed | ||
| 07/10/2024 | RSBU - Building Progress | Passed | ||
| 07/12/2024 | COT - RSEL - Electrical Final | Passed | ||
| 07/12/2024 | RSBU - Building Final | Passed |