Permit: TC-MDP-0923-01574
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6591 E CAMINO REBINA
Address NEW:
6591 E CAMINO REBINA
Apply Date:
05/22/2024
Applicant:
Christi Swenson
Description:
SFR PULT3521-3 T21-M0049
Permit Reviews
Permit Number - TC-MDP-0923-01574
Permit Status: Inspections complete
Permit Description: SFR PULT3521-3 T21-M0049
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/23/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/29/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0923-01574
Permit Status: Inspections complete
Permit Description: SFR PULT3521-3 T21-M0049
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 05/28/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 05/28/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 05/28/2024 | Post-Tension Inspection Report is required. |
| 05/28/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 05/28/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0923-01574
Permit Status: Inspections complete
Permit Description: SFR PULT3521-3 T21-M0049
| Date | Description | Comments |
|---|---|---|
| 09/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01574
Permit Description: SFR PULT3521-3 T21-M0049
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/03/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 7/3/2024 | |
| 07/03/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 7/3/2024 | |
| 07/03/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 7/3/2024 | |
| 07/10/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 07/10/2024 | COT - RSBU - Preslab | Passed | ||
| 07/10/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 08/14/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 08/14/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 08/27/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 8/27/2024 | |
| 10/01/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 10/03/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 10/21/2024 | COT - RSBU - Interior Shear Bracing | Passed | 10-21-24, okay to tape and texture. | |
| 12/31/2024 | COT - BULD - SWG Clearance | Passed | Shut off valves in place CLEARANCE SWG | |
| 01/14/2025 | COT - RSEL - Electrical Final | Passed | Passed final 1/14/25 | |
| 01/14/2025 | COT - RSEL - Grounding/Bonding | Passed | Passed final 1/14/25 | |
| 01/14/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 1/14/25 | |
| 01/14/2025 | COT - RSME - Mechanical Final | Passed | Passed final 1/14/25 | |
| 01/14/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 1/14/25 | |
| 01/14/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 01/14/2025 | RSBU - Building Final | Passed | Passed final 1/14/25 | |
| 01/14/2025 | RSBU - Building Progress | Passed | Passed final 1/14/25 |