Permit: TC-MDP-0923-01569
Permit Details
Apply Date:
03/19/2024
Applicant:
Brianna Quiroz
Description:
Harding SFR Model La Estancia (roof vent update)
Permit Reviews
Permit Number - TC-MDP-0923-01569
Permit Status: Complete
Permit Description: Harding SFR Model La Estancia (roof vent update)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/20/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 03/27/2024 | APPROVED |
10/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/15/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0923-01569
Permit Status: Complete
Permit Description: Harding SFR Model La Estancia (roof vent update)
Date | Description | Comments |
---|---|---|
10/15/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
03/27/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
10/15/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/15/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
02/16/2023 | Post-Tension Inspection Report is required. | |
10/15/2024 | Post-Tension Inspection Report is required. | |
09/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
10/15/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
10/15/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
02/16/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
10/15/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0923-01569
Permite Description: Harding SFR Model La Estancia (roof vent update)
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
05/31/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
11/22/2024 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | 11-22-24, outdoor lighting receptacles not working. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0923-01569
Permit Description: Harding SFR Model La Estancia (roof vent update)
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2024 | COT - RSPL - Rough Soil | Passed | ||
05/21/2024 | COT - RSPL - Sewer | Passed | ||
05/31/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
05/31/2024 | COT - RSEL - Electrical Underground | Passed | ||
05/31/2024 | COT - RSBU - Preslab | Passed | ||
07/09/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/15/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Corrections were made. 7/15/2024 | |
09/04/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 9/4/2024 | |
09/13/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
09/26/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO 9/26/024 | |
11/22/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-22-24, grounding/bonding approved. | |
11/22/2024 | COT - RSME - Mechanical Final | Passed | 11-22-24, approved. | |
11/22/2024 | COT - RSPL - Yard Water Line | Passed | 11-22-24, main water line inspection approved. | |
11/22/2024 | ENGR Engineering Final | Passed | CO Ready | |
11/22/2024 | RSBU - Building Progress | Passed | ||
11/25/2024 | COT - RSEL - Electrical Final | Passed | 11-25-24, building final approved. | |
11/25/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-25-24, building final approved. | |
11/25/2024 | COT - RSPL - Plumbing Final | Passed | 11-25-24, building final approved. | |
11/25/2024 | RSBU - Building Final | Passed | 11-25-24, building final approved. |