Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/20/2023
Applicant:
Ramon VALDEZ
Description:
DUPLEX DUPLVAL82 T22-M0037

Permit Reviews

Permit Number - TC-MDP-0923-01535
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Start Date Submittal Complete Date Status  
09/22/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 09/25/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0923-01535
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Date Description Comments
09/20/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0923-01535
Permite Description: DUPLEX DUPLVAL82 T22-M0037
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/09/2023 COT - RSBU - Excavation/Rebar/Zoning N/A Re-inspection required Footings are less than 12" below undisclosed soil.
10/09/2023 COT - RSBU - Preslab N/A Re-inspection required Footings are less than 12" below undisclosed soil.
10/23/2023 COT - RSBU - Firewall/Fire Barrier/Firestop N/A Partial Pass Observed o layer of 5/8" type "X" in center of walls, and one side of truss near walls; need to block and nail joints at truss location, and drywall 1-1/2" gap between truss and wall.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0923-01535
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Completed Inspections - 19
Date Description Inspector Results Comments
10/06/2023 COT - RSPL - Rough Soil Passed
10/06/2023 COT - RSPL - Sewer Passed
10/06/2023 COT - RSPL - Yard Water Line Passed
10/09/2023 COT - RSEL - Grounding/Bonding Passed
10/11/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Corrections were made. 10/11/2023
10/11/2023 COT - RSBU - Preslab Passed Corrections were made. 10/11/2023
10/23/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
10/23/2023 COT - RSBU - Roof Nailing Passed
10/27/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
04/17/2024 BULD - Electrical Clearance Passed 4/17/24: ECO TEP CLEARANCE FOR 6017 S FONTANA AL UNIT 1 AND UNIT 2.
04/29/2024 COT - RSBU - Firewall/Fire Barrier/Firestop Passed
04/29/2024 COT - RSBU - Interior Shear Bracing Passed
04/29/2024 COT - RSEL - Electrical Final Passed
04/29/2024 COT - RSEL - Outdoor Lighting Passed
04/29/2024 COT - RSME - Mechanical Final Passed
04/29/2024 COT - RSPL - Plumbing Final Passed
04/29/2024 RSBU - Building Final Passed
04/29/2024 RSBU - Building Progress Passed
04/29/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
6017_V1.PDF DOCUMENTS VIEW