Permit: TC-MDP-0923-01533
Permit Details
Apply Date:
12/18/2023
Applicant:
Stephanie Bebee
Description:
SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Permit Reviews
Permit Number - TC-MDP-0923-01533
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/04/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 01/09/2024 | APPROVED |
07/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/17/2024 | APPROVED |
01/09/2024 | RESTAMP - RESIDENTIAL v.1 | 01/09/2024 | APPROVED |
12/18/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 12/26/2023 | REQUIRES RESUBMIT |
03/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/11/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0923-01533
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Date | Description | Comments |
---|---|---|
12/18/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
12/20/2023 | Post-Tension Inspection Report is required. | |
09/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
01/09/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0923-01533
Permite Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/25/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0923-01533
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/17/2024 | COT - RSPL - Backwater Valve | Passed | Underground plumbing is properly installed and under test. Sewer is connected to underground plumbing and tracer wire is installed. Backwater valve is installed between clean outs. Okay to shade and backfill trenches. | |
01/17/2024 | COT - RSPL - Yard Water Line | Passed | Main water supply line is connected to city water system with a meter attached. | |
01/17/2024 | COT - RSPL - Sewer | Passed | Underground plumbing is properly installed and under test. Sewer is connected to underground plumbing and tracer wire is installed. Backwater valve is installed between clean outs. Okay to shade and backfill trenches. | |
01/17/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing is properly installed and under test. Sewer is connected to underground plumbing and tracer wire is installed. Backwater valve is installed between clean outs. Okay to shade and backfill trenches. | |
01/22/2024 | COT - RSEL - Electrical Underground | Passed | ||
01/22/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
01/22/2024 | COT - RSBU - Preslab | Passed | Approved PT foundation/slab | |
01/22/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Approved PT foundation/slab | |
02/15/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/15/2024 | COT - RSBU - Roof Nailing | Passed | ||
04/01/2024 | BULD - Electrical Clearance | Passed | Issued ECO Clearance for TEP to energize system. | |
04/01/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 4-1-24: Mechanical, electrical, and plumbing rough-in is complete. Repairs are made to vandalized rough-in. Okay to proceed with installation of insulation and drywall. | |
04/01/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 15 pounds of compressed air with no leaks. Okay to proceed with insulation and drywall installation. | |
05/10/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
07/22/2024 | RSBU - Building Final | Passed | ||
07/22/2024 | RSBU - Building Progress | Passed | ||
07/22/2024 | COT - RSPL - Plumbing Final | Passed | ||
07/22/2024 | COT - RSME - Mechanical Final | Passed | ||
07/22/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
07/22/2024 | COT - RSEL - Electrical Final | Passed | ||
07/24/2024 | ENGR Engineering Final | Passed | Looks good for CO |