Permit: TC-MDP-0923-01530
Permit Details
Apply Date:
09/14/2023
Applicant:
Celina Rodriguez
Description:
SFR BT1383-130 T22-M0014
Permit Reviews
Permit Number - TC-MDP-0923-01530
Permit Status: Inspections complete
Permit Description: SFR BT1383-130 T22-M0014
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/05/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/11/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0923-01530
Permit Status: Inspections complete
Permit Description: SFR BT1383-130 T22-M0014
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
10/05/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
10/05/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
10/05/2023 | Post-Installed Anchor Inspection Report is required. |
10/09/2023 | Post-Tension Inspection Report is required. |
10/09/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0923-01530
Permit Status: Inspections complete
Permit Description: SFR BT1383-130 T22-M0014
Date | Description | Comments |
---|---|---|
09/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01530
Permit Description: SFR BT1383-130 T22-M0014
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2023 | COT - RSPL - Yard Water Line | Passed | ||
10/26/2023 | COT - RSPL - Sewer | Passed | ||
10/26/2023 | COT - RSPL - Rough Soil | Passed | ||
11/03/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
11/03/2023 | COT - RSBU - Preslab | Passed | ||
11/03/2023 | COT - RSEL - Electrical Underground | Passed | ||
11/03/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
11/20/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/20/2023 | COT - RSBU - Roof Nailing | Passed | ||
12/29/2023 | BULD - Electrical Clearance | Passed | ||
01/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 1/5/24: Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation. | |
01/05/2024 | COT - RSPL - Gas Pressure Test | Passed | 1/5/24: Gas lines are under 15# of compressed air without leaks. | |
01/17/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
03/08/2024 | COT - BULD - SWG Clearance | Passed | CLEAR GAS | |
03/18/2024 | COT - RSEL - Electrical Final | Passed | Construction is completed. Mechanical, plumbing, and electrical fixtures are installed and operational. GFCI & AFCI Breakers are installed in electrical panel for kitchen, bathroom, garage & exterior outlets, and for bedroom outlets. Okay to issue Certificate of Occupancy once all other departments have completed their inspections and approved for occupancy. | |
03/18/2024 | COT - RSEL - Outdoor Lighting | Passed | Exterior lights are what is called out on plans they are properly installed and operational. | |
03/18/2024 | COT - RSME - Mechanical Final | Passed | Construction is completed. Mechanical, plumbing, and electrical fixtures are installed and operational. GFCI & AFCI Breakers are installed in electrical panel for kitchen, bathroom, garage & exterior outlets, and for bedroom outlets. Okay to issue Certificate of Occupancy once all other departments have completed their inspections and approved for occupancy. | |
03/18/2024 | COT - RSPL - Plumbing Final | Passed | Construction is completed. Mechanical, plumbing, and electrical fixtures are installed and operational. GFCI & AFCI Breakers are installed in electrical panel for kitchen, bathroom, garage & exterior outlets, and for bedroom outlets. Okay to issue Certificate of Occupancy once all other departments have completed their inspections and approved for occupancy. | |
03/18/2024 | RSBU - Building Final | Passed | Construction is completed. Mechanical, plumbing, and electrical fixtures are installed and operational. GFCI & AFCI Breakers are installed in electrical panel for kitchen, bathroom, garage & exterior outlets, and for bedroom outlets. Okay to issue Certificate of Occupancy once all other departments have completed their inspections and approved for occupancy. | |
03/18/2024 | RSBU - Building Progress | Passed | Construction is completed. Mechanical, plumbing, and electrical fixtures are installed and operational. GFCI & AFCI Breakers are installed in electrical panel for kitchen, bathroom, garage & exterior outlets, and for bedroom outlets. Okay to issue Certificate of Occupancy once all other departments have completed their inspections and approved for occupancy. | |
03/18/2024 | ENGR Engineering Final | Passed |