Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Model Building Permit
Apply Date:
10/17/2023
Applicant:
Description:
SFR MER1301600 T21-M0073 REV1 roof covering change

Permit Reviews

Permit Number - TC-MDP-0923-01504
Permit Status: Issued
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Start Date Submittal Complete Date Status  
04/17/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/17/2024 APPROVED Review Details
10/17/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 10/23/2023 APPROVED Review Details
10/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/22/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0923-01504
Permit Status: Issued
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Date Description Comments
10/17/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/17/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/17/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/17/2024 Post-Tension Inspection Report is required.
10/04/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
10/22/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/17/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
10/04/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
04/17/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/17/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-MDP-0923-01504
Permite Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
04/19/2024 RSBU - Building Progress N/A Not Applicable
04/19/2024 COT - RSPL - Gas Pressure Test N/A Re-inspection required Gauge has less than one pound of pressure.
04/19/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required Obtain gas pressure test inspection approval.
04/19/2024 COT - RSME - Mechanical Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0923-01504
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/13/2024 COT - RSPL - Yard Water Line Passed
02/13/2024 COT - RSPL - Rough Soil Passed
02/28/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
02/28/2024 COT - RSBU - Preslab Passed
02/28/2024 COT - RSEL - Grounding/Bonding Passed
02/28/2024 COT - RSEL - Electrical Underground Passed
03/19/2024 COT - RSBU - Roof Nailing Passed
03/19/2024 COT - RSBU - Exterior Clips/Sheathing Passed
03/22/2024 COT - RSPL - Sewer Passed
04/19/2024 BULD - Electrical Clearance Passed
04/19/2024 COT - RSPL - Backwater Valve Passed
04/22/2024 COT - RSPL - Gas Pressure Test Passed
04/22/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/06/2024 COT - RSBU - Interior Shear Bracing Passed Drywall for interior shear walls is properly installed and screwed off per plan requirements.
06/12/2024 COT - BULD - SWG Clearance Passed Gas valves are installed in kitchen for range, laundry room for clothes dryer, and in garage for water heater. Okay to install meter. SWG Clearance given to Southwest Gas.
07/03/2024 COT - RSME - Mechanical Final Passed All romex cabling used for circuit identification needs to removed from inside the electrical panel.
07/03/2024 COT - RSEL - Outdoor Lighting Passed Outdoor lighting is properly installed and operational per plans.
07/03/2024 COT - RSPL - Plumbing Final Passed
07/03/2024 ENGR Engineering Final Passed
07/08/2024 COT - RSEL - Electrical Final Passed
07/08/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
145855 PT LOT 172 COMPLETE-2024-04-16_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 172 APPLICATION_V1.PDF DOCUMENTS VIEW
LOT 172 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 172 SPECIAL INSPECTION CERTIFICATE-2023-10-17_V1.PDF DOCUMENTS VIEW