Permit: TC-MDP-0923-01501
Permit Details
Apply Date:
11/27/2023
Applicant:
Daria Hopkins
Description:
SFR MER1301600 T21-M0073 REV1 roof covering change
Permit Reviews
Permit Number - TC-MDP-0923-01501
Permit Status: Complete
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/20/2024 | APPROVED |
11/27/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 12/04/2023 | APPROVED |
10/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0923-01501
Permit Status: Complete
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Date | Description | Comments |
---|---|---|
11/27/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
11/27/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
11/28/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
11/27/2023 | Post-Tension Inspection Report is required. | |
09/08/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
11/22/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
11/22/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
10/21/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
11/28/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0923-01501
Permit Description: SFR MER1301600 T21-M0073 REV1 roof covering change
Total Completed Inspections - 22