Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
03/22/2024
Applicant:
Description:
SFR RKF55C T21-M0085

Permit Reviews

Permit Number - TC-MDP-0923-01477
Permit Status: Inspections complete
Permit Description: SFR RKF55C T21-M0085
Start Date Submittal Complete Date Status  
03/22/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/01/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0923-01477
Permit Status: Inspections complete
Permit Description: SFR RKF55C T21-M0085
Total Outstanding Activity Conditions - 5
Date Name
03/25/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
03/25/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/25/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
03/25/2024 Post-Tension Inspection Report is required.
03/25/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0923-01477
Permit Status: Inspections complete
Permit Description: SFR RKF55C T21-M0085
Date Description Comments
09/01/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
03/22/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
08/08/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01477
Permite Description: SFR RKF55C T21-M0085
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
07/15/2024 COT - RSBU - Roof Nailing N/A Re-inspection required 7/15/24: cut nail needed at bedroom 2 walk in closet. Trust t40 in garage needs engineering fix for broken/cracked webbing.
07/15/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 7/15/24: cut nail needed at bedroom 2 walk in closet. Trust t40 in garage needs engineering fix for broken/cracked webbing.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0923-01477
Permit Description: SFR RKF55C T21-M0085
Total Completed Inspections - 22
Date Description Inspector Results Comments
05/20/2024 COT - RSPL - Backwater Valve Passed
05/20/2024 COT - RSPL - Yard Water Line Passed
05/20/2024 COT - RSPL - Sewer Passed
05/20/2024 COT - RSPL - Rough Soil Passed
05/30/2024 COT - RSBU - Preslab Passed
05/30/2024 COT - RSEL - Electrical Underground Passed
05/30/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
05/30/2024 COT - RSEL - Grounding/Bonding Passed
07/22/2024 COT - RSBU - Roof Nailing Passed 7/22/24: Bottom plate in Bedroom #2 has been secured to concrete floor. Truss webbing on truss T40 in garage has been reinforced on both sides per engineered specifications. Okay to proceed with rough-in of mechanical, plumbing, and electrical.
07/22/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 7/22/24: Bottom plate in Bedroom #2 has been secured to concrete floor. Truss webbing on truss T40 in garage has been reinforced on both sides per engineered specifications. Okay to proceed with rough-in of mechanical, plumbing, and electrical.
08/21/2024 COT - RSPL - Gas Pressure Test Passed Temporary GFCI receptacles and breakers missing at panel. Bonding wire from meter to gas line missing.
08/23/2024 BULD - Electrical Clearance Passed 8/23/24: Electricians have installed bonding wire on gas line, temp power receptacle, and breakers on panel box. Okay to proceed with insulation and drywall installation throughout building.
08/23/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 8/23/24: Electricians have installed bonding wire on gas line, temp power receptacle, and breakers on panel box. Okay to proceed with insulation and drywall installation throughout building.
09/11/2024 COT - RSBU - Interior Shear Bracing Passed Drywall is properly secured to studs per shear wall detail on plan. Okay to proceed with tape, texture, and paint.
11/01/2024 COT - BULD - SWG Clearance Passed 11-1-24, approved for Southwest Gas connection.
11/15/2024 COT - RSEL - Electrical Final Passed 11-15-24, electrical final approved.
11/15/2024 COT - RSEL - Outdoor Lighting Passed 11-15-24, electrical final approved.
11/15/2024 COT - RSME - Mechanical Final Passed 11-15-24, mechanical final approved.
11/15/2024 COT - RSPL - Plumbing Final Passed 11-15-24, mechanical final approved.
11/15/2024 RSBU - Building Progress Passed
11/19/2024 RSBU - Building Final Passed 11-19-24, building final approved
11/21/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT.-2024-03-22_V1.PDF DOCUMENTS VIEW