New Residential Model Plan (Model master plan TC-MDP-1224-01413) Rev 2

Permit Reviews

Permit Number - TC-MDP-0825-00434
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01413) Rev 2
Start Date Submittal Complete Date Status  
01/29/2026 SITE FROM MODEL PERMIT - SUBDIVISION v.1 02/06/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0825-00434
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01413) Rev 2
Total Outstanding Activity Conditions - 3
Date Name
02/03/2026 Post-Installed Anchor Inspection Report is required.
02/03/2026 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
08/15/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Conditions

Permit Number - TC-MDP-0825-00434
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01413) Rev 2
Date Description Comments
08/15/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
08/15/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/15/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
02/03/2026 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0825-00434
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01413) Rev 2
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/23/2026 COT - RSPL - Yard Water Line Passed Passed 2/23/26
02/23/2026 COT - RSPL - Sewer Passed Passed 2/23/26
02/23/2026 COT - RSPL - Rough Soil Passed Passed 2/23/26
02/27/2026 BULD - Electrical Clearance Passed 2/27/2026
Clearance TEP ECO.
02/27/2026 COT - RSBU - Excavation/Rebar/Zoning Passed 2/27/2026
Approved per site plan, foundation details. Okay for concrete placement.
02/27/2026 COT - RSBU - Preslab Passed 2/27/2026
Approved per site plan, foundation details. Okay for concrete placement.
02/27/2026 COT - RSEL - Electrical Underground Passed
02/27/2026 COT - RSEL - Grounding/Bonding Passed 2/27/2026
Connected to MSP.
03/12/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 03/12/2026
Approved per plan.
03/12/2026 COT - RSBU - Roof Nailing Passed 03/12/2026
Approved per plan.
03/25/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 3.25.26
Approved
03/25/2026 COT - RSPL - Gas Pressure Test Passed 3.25.26
approved
04/08/2026 COT - RSBU - Interior Shear Bracing Passed 04/08/2026
Approved per plan, ok to tape & texture.
05/13/2026 COT - BULD - SWG Clearance Passed
05/21/2026 COT - RSEL - Electrical Final Passed Passed 5/21/26
05/21/2026 COT - RSEL - Outdoor Lighting Passed Passed 5/21/26
05/21/2026 COT - RSME - Mechanical Final Passed Passed 5/21/26
05/21/2026 COT - RSPL - Plumbing Final Passed Passed 5/21/26
05/21/2026 ENGR Engineering Final Passed
05/21/2026 RSBU - Building Final Passed Passed 5/21/26
05/21/2026 RSBU - Building Progress Passed Passed 5/21/26

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
1_SEWER PERMIT_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2026-01-26_V1.PDF DOCUMENTS VIEW