Permit: TC-MDP-0824-00937
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
9125 E CATALINA HY BLDG 149
Address NEW:
9125 E CATALINA HY BLDG 149
Apply Date:
09/17/2024
Applicant:
Cassidy Fenton
Description:
SFR CASITA2X2 T20-M0045
Permit Reviews
Permit Number - TC-MDP-0824-00937
Permit Status: Complete
Permit Description: SFR CASITA2X2 T20-M0045
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 10/02/2024 | APPROVED |
| 07/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/25/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0824-00937
Permit Status: Complete
Permit Description: SFR CASITA2X2 T20-M0045
| Date | Description | Comments |
|---|---|---|
| 09/27/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 09/27/2024 | Post-Tension Inspection Report is required. | |
| 08/29/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/29/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 09/27/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00937
Permite Description: SFR CASITA2X2 T20-M0045
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2024 | RSBU - Building Progress | N/A | Not Applicable | |
| 12/11/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/11/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00937
Permit Description: SFR CASITA2X2 T20-M0045
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2024 | COT - RSPL - Rough Soil | Passed | ||
| 12/04/2024 | COT - RSPL - Sewer | Passed | ||
| 12/04/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 12/11/2024 | COT - RSBU - Preslab | Passed | ||
| 12/11/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 12/11/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 01/31/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 1-31-25, exterior clip/sheathing approved. Okay to continue construction | |
| 01/31/2025 | COT - RSBU - Roof Nailing | Passed | 1-31-25, exterior clip/sheathing & roof nailing approved. Okay to continue construction | |
| 03/19/2025 | BULD - Electrical Clearance | Passed | 3-19-25, panel okay to be energized. ECO clearance issued to TEP. | |
| 03/19/2025 | COT - RSEL - Grounding/Bonding | Passed | 3-19-25, grounding/bonding approved | |
| 03/21/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3-21-25, approved . Okay to continue with construction | |
| 04/10/2025 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 06/13/2025 | COT - RSEL - Electrical Final | Passed | ||
| 06/13/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/13/2025 | COT - RSME - Mechanical Final | Passed | ||
| 06/13/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 06/13/2025 | RSBU - Building Final | Passed | ||
| 08/04/2025 | ENGR Engineering Final | Passed | Building is complete in accordance with approved plans. |