Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/12/2024
Applicant:
Cassidy Fenton
Description:
DUPLEX CASITA1X1 T20-M0044 (Model Template TC-MDP-0824-00852)

Permit Reviews

Permit Number - TC-MDP-0824-00932
Permit Status: Complete
Permit Description: DUPLEX CASITA1X1 T20-M0044 (Model Template TC-MDP-0824-00852)
Start Date Submittal Complete Date Status  
07/14/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/14/2025 APPROVED Review Details
07/09/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 07/09/2025 APPROVED Review Details
06/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/26/2025 REQUIRES RESUBMIT Review Details
09/13/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 09/18/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0824-00932
Permit Status: Complete
Permit Description: DUPLEX CASITA1X1 T20-M0044 (Model Template TC-MDP-0824-00852)
Date Description Comments
09/13/2024 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
09/17/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
09/17/2024 Post-Tension Inspection Report is required.
08/28/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/28/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
09/17/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00932
Permite Description: DUPLEX CASITA1X1 T20-M0044 (Model Template TC-MDP-0824-00852)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
12/06/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable
12/18/2024 COT - BULD - SWG Clearance N/A Not Applicable
12/18/2024 BULD - Electrical Clearance N/A Canceled
12/18/2024 COT - RSEL - Grounding/Bonding N/A Canceled

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00932
Permit Description: DUPLEX CASITA1X1 T20-M0044 (Model Template TC-MDP-0824-00852)
Total Completed Inspections - 19
Date Description Inspector Results Comments
10/28/2024 COT - RSPL - Yard Water Line Passed 10/28/24: plumbing underground per plans ok to proceed with backfill. Shading required
10/28/2024 COT - RSPL - Sewer Passed 10/28/24: plumbing underground per plans ok to proceed with backfill. Shading required
10/28/2024 COT - RSPL - Rough Soil Passed 10/28/24: plumbing underground per plans ok to proceed with backfill. Shading required
11/08/2024 COT - RSBU - Preslab Passed
11/08/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
11/08/2024 RSBU - Building Progress Passed
11/08/2024 COT - RSEL - Electrical Underground Passed
12/06/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
12/06/2024 COT - RSBU - Roof Nailing Passed
01/29/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Mechanical, electrical, and plumbing rough-in is complete per plans. Okay to proceed with installation of insulation and drywall on walls and ceilings.
01/29/2025 BULD - Electrical Clearance Passed ECO Clearance issued to TEP for service at 9125 E Catalina Hwy Building 176.
01/29/2025 COT - RSEL - Grounding/Bonding Passed Ground wire is properly secured to Ufer ground.
02/14/2025 COT - RSBU - Interior Shear Bracing Passed Drywall for interior shear drywall is properly secured to studs with screws per the plan requirements. Okay to proceed with tape, texture, and paint.
06/04/2025 ENGR Engineering Final Passed
06/04/2025 COT - RSEL - Outdoor Lighting Passed
06/09/2025 COT - RSEL - Electrical Final Passed Passed final 6/9/25
06/09/2025 COT - RSME - Mechanical Final Passed Passed final 6/9/25
06/09/2025 COT - RSPL - Plumbing Final Passed Passed final 6/9/25
06/09/2025 RSBU - Building Final Passed Passed final 6/9/25

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
PT BLDG 176-177 COMPLETE-2025-07-08_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SITE PLAN BLDGS 176-177_V1.PDF DOCUMENTS VIEW
SIC BLDGS 176-177-2024-09-12_V1.PDF DOCUMENTS VIEW