Permit: TC-MDP-0824-00858
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
9125 E CATALINA HY BLDG 4
Address NEW:
9125 E CATALINA HY BLDG 4
Apply Date:
08/09/2024
Applicant:
Cassidy Fenton
Description:
Six Bay Garage T20-M0047
Permit Reviews
Permit Number - TC-MDP-0824-00858
Permit Status: Complete
Permit Description: Six Bay Garage T20-M0047
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/12/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 08/20/2024 | APPROVED |
| 11/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/06/2025 | APPROVED |
| 08/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/28/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0824-00858
Permit Status: Complete
Permit Description: Six Bay Garage T20-M0047
| Date | Description | Comments |
|---|---|---|
| 08/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00858
Permite Description: Six Bay Garage T20-M0047
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2024 | COT - RSPL - Yard Water Line | N/A | Not Applicable | |
| 08/28/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 08/28/2024 | COT - RSPL - Sewer | N/A | Not Applicable | |
| 08/28/2024 | COT - RSPL - Rough Soil | N/A | Not Applicable | |
| 04/08/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | does not use gas |
| 04/09/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00858
Permit Description: Six Bay Garage T20-M0047
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2024 | COT - RSBU - Preslab | Passed | ||
| 08/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 10/25/2024 | RSBU - Building Progress | Passed | main water lines for phase Two North side. | |
| 04/08/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Passed 4/8/25 | |
| 04/09/2025 | BULD - Electrical Clearance | Passed | ECO | |
| 04/09/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/09/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 04/10/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 07/17/2025 | RSBU - Building Final | Passed | ||
| 07/17/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 07/17/2025 | COT - RSME - Mechanical Final | Passed | ||
| 07/17/2025 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/17/2025 | COT - RSEL - Electrical Final | Passed | ||
| 07/21/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed 7/21/25 | |
| 08/25/2025 | ENGR Engineering Final | Passed |