Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
08/09/2024
Applicant:
Cassidy Fenton
Description:
Six Bay Garage T20-M0047

Permit Reviews

Permit Number - TC-MDP-0824-00858
Permit Status: Complete
Permit Description: Six Bay Garage T20-M0047
Start Date Submittal Complete Date Status  
08/12/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 08/20/2024 APPROVED Review Details
11/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/06/2025 APPROVED Review Details
08/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/28/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-0824-00858
Permit Status: Complete
Permit Description: Six Bay Garage T20-M0047
Date Description Comments
08/08/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00858
Permite Description: Six Bay Garage T20-M0047
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
08/28/2024 COT - RSPL - Yard Water Line N/A Not Applicable
08/28/2024 COT - RSEL - Electrical Underground N/A Not Applicable
08/28/2024 COT - RSPL - Sewer N/A Not Applicable
08/28/2024 COT - RSPL - Rough Soil N/A Not Applicable
04/08/2025 COT - BULD - SWG Clearance N/A Not Applicable does not use gas
04/09/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00858
Permit Description: Six Bay Garage T20-M0047
Total Completed Inspections - 15
Date Description Inspector Results Comments
08/28/2024 COT - RSBU - Preslab Passed
08/28/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
10/25/2024 RSBU - Building Progress Passed main water lines for phase Two North side.
04/08/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Passed 4/8/25
04/09/2025 BULD - Electrical Clearance Passed ECO
04/09/2025 COT - RSEL - Grounding/Bonding Passed
04/09/2025 COT - RSBU - Roof Nailing Passed
04/10/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
07/17/2025 RSBU - Building Final Passed
07/17/2025 COT - RSPL - Plumbing Final Passed
07/17/2025 COT - RSME - Mechanical Final Passed
07/17/2025 COT - RSBU - Interior Shear Bracing Passed
07/17/2025 COT - RSEL - Electrical Final Passed
07/21/2025 COT - RSEL - Outdoor Lighting Passed Passed 7/21/25
08/25/2025 ENGR Engineering Final Passed