Permit: TC-MDP-0823-01465
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
10240 E CIVANO WASH TR
Address NEW:
10240 E CIVANO WASH TR
Apply Date:
08/31/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR F40F22 T22-M0026
Permit Reviews
Permit Number - TC-MDP-0823-01465
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/31/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 09/05/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0823-01465
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 08/31/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/31/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/31/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 08/31/2023 | Post-Tension Inspection Report is required. |
| 08/31/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 08/31/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0823-01465
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
| Date | Description | Comments |
|---|---|---|
| 08/01/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01465
Permit Description: SFR F40F22 T22-M0026
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 03/12/2024 | COT - RSPL - Rough Soil | Passed | ||
| 03/18/2024 | COT - RSPL - Sewer | Passed | Sewer line is connected to city sewer system and under pressure test with no leaks in pipes. Okay to shade pipe and backfill trench. | |
| 03/18/2024 | COT - RSPL - Yard Water Line | Passed | Main water line is connected to City water supply with a meter and under street pressure. Blue tracer wire is installed. Okay to shade pipe and backfill trench. | |
| 03/20/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 03/20/2024 | COT - RSBU - Preslab | Passed | ||
| 03/20/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 03/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/16/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 04/16/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 05/07/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/07/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 05/07/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/16/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/11/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 08/26/2024 | COT - RSEL - Electrical Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | COT - RSEL - Outdoor Lighting | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | COT - RSME - Mechanical Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | COT - RSPL - Plumbing Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | ENGR Engineering Final | Passed | Move in ready | |
| 08/26/2024 | RSBU - Building Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | RSBU - Building Progress | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with the proper AFCI & GFCI breakers installed. Outdoor lighting is installed per plan and city guidelines. Okay to issue Certificate of Occupancy. |