Permit: TC-MDP-0823-01455
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12810 E TORTOISE CANYON LN
Address NEW:
12810 E TORTOISE CANYON LN
Apply Date:
08/23/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKF55F T21-M0087
Permit Reviews
Permit Number - TC-MDP-0823-01455
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/27/2023 | APPROVED |
| 08/23/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/28/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0823-01455
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 01/20/2023 | Post-Tension Inspection Report is required. |
| 01/20/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 08/23/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/23/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/23/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 08/28/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0823-01455
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
| Date | Description | Comments |
|---|---|---|
| 09/27/2023 | ISSUED WITH PDEQ CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PRIVATE SEWER #P21SD0033 IS ISSUED A DISCHARGE AUTHORIZATION BY PDEQ | |
| 08/23/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01455
Permit Description: SFR RKF55F T21-M0087
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/22/2024 | COT - RSPL - Sewer | Passed | ||
| 02/22/2024 | COT - RSPL - Rough Soil | Passed | ||
| 02/22/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 02/22/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 03/13/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are in place, Ufer ground is installed in bottom of footer, post tension cabling is spaced properly, footings are properly dug and clear of debris. Okay to pour concrete slab and footings. | |
| 03/13/2024 | COT - RSEL - Electrical Underground | Passed | Underground electrical for kitchen island is in place. Okay to pour concrete for slab and footings. | |
| 03/13/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are in place, Ufer ground is installed in bottom of footer, post tension cabling is spaced properly, footings are properly dug and clear of debris. Okay to pour concrete slab and footings. | |
| 03/13/2024 | COT - RSBU - Preslab | Passed | Concrete forms are in place, Ufer ground is installed in bottom of footer, post tension cabling is spaced properly, footings are properly dug and clear of debris. Okay to pour concrete slab and footings. | |
| 04/02/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 04/15/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 4-15-24: all items noted on last inspection have been corrected and are completed. Okay to proceed with dry-in of exterior walls. | |
| 05/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation. | |
| 05/10/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is under 15# of compressed air with no leaks. Okay to proceed. | |
| 05/28/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 06/04/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 08/19/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 08/23/2024 | COT - RSEL - Electrical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with AFCI & GFCI breakers installed where required. Outdoor lighting meets plan requirements and city regulations. Okay to issue Certificate of Occupancy. | |
| 08/23/2024 | COT - RSEL - Outdoor Lighting | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with AFCI & GFCI breakers installed where required. Outdoor lighting meets plan requirements and city regulations. Okay to issue Certificate of Occupancy. | |
| 08/23/2024 | COT - RSME - Mechanical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with AFCI & GFCI breakers installed where required. Outdoor lighting meets plan requirements and city regulations. Okay to issue Certificate of Occupancy. | |
| 08/23/2024 | COT - RSPL - Plumbing Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with AFCI & GFCI breakers installed where required. Outdoor lighting meets plan requirements and city regulations. Okay to issue Certificate of Occupancy. | |
| 08/23/2024 | ENGR Engineering Final | Passed | ||
| 08/23/2024 | RSBU - Building Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are properly installed and operational. Electrical panel is properly labeled with AFCI & GFCI breakers installed where required. Outdoor lighting meets plan requirements and city regulations. Okay to issue Certificate of Occupancy. | |
| 08/26/2024 | RSBU - Building Progress | Passed |