Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
08/18/2023
Applicant:
Vance Goodman
Description:
2231 Sleepy Hollow Estates

Permit Reviews

Permit Number - TC-MDP-0823-01430
Permit Status: Complete
Permit Description: 2231 Sleepy Hollow Estates
Start Date Submittal Complete Date Status  
08/18/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 08/25/2023 REQUIRES RESUBMIT Review Details
12/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/30/2024 REQUIRES RESUBMIT Review Details
09/06/2023 RESTAMP - RESIDENTIAL v.1 09/07/2023 APPROVED Review Details
09/06/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.2 09/06/2023 APPROVED Review Details
01/15/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 01/16/2025 APPROVED Review Details
01/24/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/24/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0823-01430
Permit Status: Complete
Permit Description: 2231 Sleepy Hollow Estates
Date Description Comments
05/17/2023 Post-Installed Anchor Inspection Report is required.
12/31/2024 Post-Installed Anchor Inspection Report is required.
05/17/2023 Post-Tension Inspection Report is required.
12/31/2024 Post-Tension Inspection Report is required.
05/17/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
12/31/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/18/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
12/31/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
05/17/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
12/31/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0823-01430
Permite Description: 2231 Sleepy Hollow Estates
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
06/14/2024 COT - RSEL - Electrical Underground N/A Partial Pass Secondaries from transformer to service panel approved. Okay to backfill progress areas. 6/14/2024
12/13/2024 COT - BULD - SWG Clearance N/A Not Applicable .
12/13/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable
12/30/2024 ENGR Engineering Final N/A Partial Pass Okay for TCO level 4

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0823-01430
Permit Description: 2231 Sleepy Hollow Estates
Total Completed Inspections - 20
Date Description Inspector Results Comments
02/16/2024 COT - RSPL - Rough Soil Passed Okay to backfill. Shading required. 2/16/2024
03/06/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 3/6/24: Reinforcement per plan ok to pour.
03/06/2024 COT - RSBU - Preslab Passed 3/6/24: Reinforcement per plan ok to pour.
03/06/2024 COT - RSEL - Grounding/Bonding Passed TEST 1
05/20/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/20/2024 COT - RSBU - Roof Nailing Passed
07/10/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
07/29/2024 COT - RSBU - Interior Shear Bracing Passed
08/01/2024 COT - RSPL - Sewer Passed
08/01/2024 COT - RSPL - Yard Water Line Passed
10/11/2024 BULD - Electrical Clearance Passed 10/11/24: TEP ECO CLEARANCE FOR 615 W ALTURAS ST BLDG 22 UNITS 22101 and unit 22102
10/11/2024 COT - RSEL - Electrical Underground Passed
12/19/2024 RSBU - Building Progress Passed
12/20/2024 COT - RSEL - Electrical Final Passed
12/20/2024 COT - RSEL - Outdoor Lighting Passed
12/20/2024 COT - RSME - Mechanical Final Passed
12/20/2024 COT - RSPL - Plumbing Final Passed
12/23/2024 RSBU - Building Final Passed 12/23/24. Passed, ok for level four TCO for DP.
12/23/2024 COT - FCON - Sprinkler - Final Passed
06/12/2025 ENGR Engineering Final Passed