Permit: TC-MDP-0823-01406
Permit Details
Apply Date:
08/23/2023
Applicant:
Andrea Flood
Description:
SFR F60B22 T22-M0027
Permit Reviews
Permit Number - TC-MDP-0823-01406
Permit Status: Inspections complete
Permit Description: SFR F60B22 T22-M0027
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/24/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/29/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0823-01406
Permit Status: Inspections complete
Permit Description: SFR F60B22 T22-M0027
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
08/24/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
08/24/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/24/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
08/24/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
08/28/2023 | Post-Tension Inspection Report is required. |
08/28/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0823-01406
Permit Status: Inspections complete
Permit Description: SFR F60B22 T22-M0027
Date | Description | Comments |
---|---|---|
08/16/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01406
Permit Description: SFR F60B22 T22-M0027
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2023 | COT - RSPL - Backwater Valve | Passed | ||
10/03/2023 | COT - RSPL - Rough Soil | Passed | ||
10/03/2023 | COT - RSPL - Sewer | Passed | ||
10/06/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
10/06/2023 | COT - RSBU - Preslab | Passed | ||
10/06/2023 | COT - RSEL - Electrical Underground | Passed | ||
10/06/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
11/02/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/02/2023 | COT - RSBU - Roof Nailing | Passed | ||
11/28/2023 | COT - RSPL - Yard Water Line | Passed | ||
11/28/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
11/30/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
12/06/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
12/15/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
02/14/2024 | COT - RSME - Mechanical Final | Passed | ||
02/14/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
03/06/2024 | COT - RSEL - Electrical Final | Passed | ||
03/06/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
03/06/2024 | COT - RSPL - Plumbing Final | Passed | ||
03/06/2024 | RSBU - Building Progress | Passed | ||
03/08/2024 | RSBU - Building Final | Passed | 3/8/24: Construction of new home is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Outdoor lighting is per plans. Engineering inspection is scheduled for today,but has not been recorded as of yet. Okay to issue Certificate of Occupancy once engineering inspection has been completed and approved. | |
03/08/2024 | ENGR Engineering Final | Passed |