Permit: TC-MDP-0823-01402
Permit Details
Apply Date:
08/23/2023
Applicant:
Paul Schmidt
Description:
SFR F40G22 T22-M0025 Revision-Truss Calcs
Permit Reviews
Permit Number - TC-MDP-0823-01402
Permit Status: Inspections complete
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/23/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/28/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0823-01402
Permit Status: Inspections complete
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
08/23/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
08/23/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/23/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
08/23/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
08/28/2023 | Post-Tension Inspection Report is required. |
08/28/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0823-01402
Permit Status: Inspections complete
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Date | Description | Comments |
---|---|---|
08/16/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01402
Permite Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2024 | COT - BULD - SWG Clearance | N/A | Re-inspection required | 7/18/24: no access door locked |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01402
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/12/2024 | COT - RSPL - Backwater Valve | Passed | ||
03/12/2024 | COT - RSPL - Rough Soil | Passed | ||
03/18/2024 | COT - RSPL - Sewer | Passed | Sewer line is connected to city sewer system and under pressure test with no leaks in pipes. Okay to shade pipe and backfill trench. | |
03/18/2024 | COT - RSPL - Yard Water Line | Passed | Main water line is connected to City water supply with a meter and under street pressure. Blue tracer wire is installed. Okay to shade pipe and backfill trench. | |
03/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
03/20/2024 | COT - RSEL - Electrical Underground | Passed | ||
03/20/2024 | COT - RSBU - Preslab | Passed | ||
03/20/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
04/16/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
04/16/2024 | COT - RSBU - Roof Nailing | Passed | ||
05/17/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is pressurized to 15 pounds of air with no leaks. Okay to proceed. | |
05/17/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in are complete. Okay to proceed with insulation and drywall installation. | |
05/17/2024 | BULD - Electrical Clearance | Passed | ECO Clearance sent to TEP for electrical panel to be energized. | |
06/03/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
07/19/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
08/30/2024 | COT - RSEL - Electrical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
08/30/2024 | COT - RSEL - Outdoor Lighting | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
08/30/2024 | COT - RSME - Mechanical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
08/30/2024 | COT - RSPL - Plumbing Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
08/30/2024 | RSBU - Building Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
08/30/2024 | RSBU - Building Progress | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. Outdoor lighting is installed per plans and city regulations. Okay to issue Certificate of Occupancy for this project. | |
09/09/2024 | ENGR Engineering Final | Passed | Move in ready |