Permit: TC-MDP-0823-01319
Permit Details
Apply Date:
09/15/2023
Applicant:
Stephanie Bebee
Description:
SFR PVCS1041 T22-M0050
Permit Reviews
Permit Number - TC-MDP-0823-01319
Permit Status: Complete
Permit Description: SFR PVCS1041 T22-M0050
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/29/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/29/2023 | APPROVED |
09/15/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 09/19/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0823-01319
Permit Status: Complete
Permit Description: SFR PVCS1041 T22-M0050
Date | Description | Comments |
---|---|---|
01/03/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
09/18/2023 | Post-Tension Inspection Report is required. | |
08/03/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
09/18/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0823-01319
Permite Description: SFR PVCS1041 T22-M0050
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2023 | COT - RSPL - Rough Soil | N/A | Re-inspection required | Plumbing is not per plan; discussed with super and plumber. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0823-01319
Permit Description: SFR PVCS1041 T22-M0050
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2023 | COT - RSPL - Yard Water Line | Passed | ||
10/11/2023 | COT - RSPL - Sewer | Passed | ||
10/11/2023 | COT - RSPL - Backwater Valve | Passed | ||
10/12/2023 | COT - RSPL - Rough Soil | Passed | 10/12/23: revision in review for clean out relocation okay to proceed at own risk | |
10/18/2023 | COT - RSEL - Grounding/Bonding | Passed | Footing are properly dug. Rebar reinforcement, post-tension cabling, and shear wall hold downs are in place. Ufer ground is properly positioned in footing. Okay to proceed with concrete pour. | |
10/18/2023 | COT - RSEL - Electrical Underground | Passed | underground electrical for kitchen island complete. | |
10/18/2023 | COT - RSBU - Preslab | Passed | Footing are properly dug. Rebar reinforcement, post-tension cabling, and shear wall hold downs are in place. Ufer ground is properly positioned in footing. Okay to proceed with concrete pour. | |
10/18/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footing are properly dug. Rebar reinforcement, post-tension cabling, and shear wall hold downs are in place. Ufer ground is properly positioned in footing. Okay to proceed with concrete pour. | |
11/27/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/27/2023 | COT - RSBU - Roof Nailing | Passed | Roof sheathing is properly nailed off. H2.5 clips are installed on all roof joists. | |
01/31/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
01/31/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
02/26/2024 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
02/26/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
03/15/2024 | BULD - Electrical Clearance | Passed | Electrical panel is installed with temporary power box. Okay to energize panel. TEP ECO Clearance issued for electrical panel. | |
05/09/2024 | COT - BULD - SWG Clearance | Passed | ||
05/15/2024 | COT - RSEL - Electrical Final | Passed | ||
05/15/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
05/15/2024 | COT - RSME - Mechanical Final | Passed | ||
05/15/2024 | COT - RSPL - Plumbing Final | Passed | ||
05/15/2024 | ENGR Engineering Final | Passed | ||
05/15/2024 | RSBU - Building Final | Passed | ||
05/15/2024 | RSBU - Building Progress | Passed |