Permit: TC-MDP-0726-00563
Permit Details
Status:
Inspections
Type:
Model Building Permit
Address:
6267 S BLUE ANGELS AV
Address NEW:
6267 S BLUE ANGELS AV
Apply Date:
07/14/2026
Applicant:
Celina Rodriguez
Description:
Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
Permit Reviews
Permit Number - TC-MDP-0726-00563
Permit Status: Inspections
Permit Description: Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 07/23/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0726-00563
Permit Status: Inspections
Permit Description: Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 07/13/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 07/13/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/23/2026 | Prior to Final - Required Documents - Post-Installed Anchor Inspection Report is required. |
Conditions
Permit Number - TC-MDP-0726-00563
Permit Status: Inspections
Permit Description: Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
| Date | Description | Comments |
|---|---|---|
| 07/13/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 07/13/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0726-00563
Permite Description: Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2026 | BULD - Electrical Clearance | N/A | Re-inspection required | 9-3-26 Breaker is required to be labeled at panel |
| 09/03/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 9-3-26 Fresh air intake should be strapped 4 feet from opening at 4 foot intervals* vapor barrier needs to be sealed above head throughout *bang plates are required at marked location.. reinspection required |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0726-00563
Permit Description: Cielo Reserves SFR Model Plan 1740-130 (Model Master Plan TC-MDP-0526-00348)
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2026 | COT - RSPL - Yard Water Line | Passed | ||
| 08/03/2026 | COT - RSPL - Rough Soil | Passed | 08/03/2026 Holding under test. Okay to backfill, shading required. |
|
| 08/03/2026 | COT - RSPL - Sewer | Passed | 08/03/2026 Holding under test to HCS. Okay to backfill, shading required. |
|
| 08/07/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 8-7-26 Okay to pour | |
| 08/07/2026 | COT - RSBU - Preslab | Passed | 8-7-26 Okay to pour | |
| 08/07/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 08/13/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 08/13/2026 | COT - RSBU - Roof Nailing | Passed | ||
| 09/03/2026 | COT - RSPL - Gas Pressure Test | Passed | 9-3-26 gas pressure test approved | |
| 09/03/2026 | RSBU - Building Progress | Passed | ||
| 09/04/2026 | BULD - Electrical Clearance | Passed | 9-4-26 ECO Clearance approved | |
| 09/08/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 9-8-26 all corrections were made OK to proceed | |
| 09/22/2026 | COT - RSBU - Interior Shear Bracing | Passed | 9-22-26 all corrections have been made OK to proceed |