Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
3065 E MISSOURI ST
Apply Date:
07/28/2023
Applicant:
Inai Maldonado
Description:
LUMO III New SFR

Permit Reviews

Permit Number - TC-MDP-0723-01251
Permit Status: Complete
Permit Description: LUMO III New SFR
Start Date Submittal Complete Date Status  
07/28/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 07/31/2023 REQUIRES RESUBMIT Review Details
08/14/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.2 08/15/2023 APPROVED Review Details
09/22/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/22/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0723-01251
Permit Status: Complete
Permit Description: LUMO III New SFR
Total Outstanding Activity Conditions - 1
Date Name
08/24/2023 Associated Conditions DS0920 Septic shall have 100 ft setback to wells, 5 ft setback from property line, 50 ft setback from property line if no central water source, and 50 ft setback to washes that drains more than 20 acres. Applied | Notice | 06/23/2022 DS0945 Approval has been granted solely for a Construction Authorization and/or a Discharge Authorization in accordance with A.A.C. § R18-9-A301. Construction or discharging without local regulatory approval from Development Services in regard to zoning, grading, flood control and other applicable regulatory requirements may result in a violation of local ordinances and subject the applicant to penalties of up to $10,000.00 per instance per day. Applied | Notice | 06/23/2022 DS0950 Discharge authorization is required prior to building final inspection or certificate of occupancy. Applied | Notice | 06/23/2022

Conditions

Permit Number - TC-MDP-0723-01251
Permit Status: Complete
Permit Description: LUMO III New SFR
Date Description Comments
07/31/2023 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact.
05/01/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0723-01251
Permite Description: LUMO III New SFR
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
09/25/2023 COT - RSBU - Interior Shear Bracing N/A Not Applicable Not required for this project. No interior shear walls on approved drawings.
09/28/2023 RSPL - Plumbing Progress N/A Not Applicable
09/28/2023 COT - BULD - SWG Clearance N/A Not Applicable
09/28/2023 COT - RSPL - Gas Pressure Test N/A Not Applicable
09/28/2023 RSBU - Building Progress N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0723-01251
Permit Description: LUMO III New SFR
Total Completed Inspections - 11
Date Description Inspector Results Comments
08/25/2023 COT - RSEL - Electrical Underground Passed
08/25/2023 COT - RSPL - Rough Soil Passed under ground plumbing pass. okay to backfill. shading required. 8/25/2023
08/29/2023 COT - RSPL - Sewer Passed
08/29/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
08/29/2023 COT - RSBU - Preslab Passed
08/29/2023 COT - RSEL - Grounding/Bonding Passed
09/25/2023 BULD - Electrical Clearance Passed Electrical panel with meter box are installed on side of house. Electrical rough-in is complete. Okay to energize panel.
09/25/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Roof decking is properly nailed off. Exterior sheathing is properly nailed off. H2.5 clips are installed on all roof rafters.
09/25/2023 COT - RSBU - Roof Nailing Passed Roof decking is properly nailed off. Exterior sheathing is properly nailed off. H2.5 clips are installed on all roof rafters.
09/28/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
09/28/2023 COT - RSPL - Yard Water Line Passed

Documents

File Name Document Type  
TRUSS_CALCS_3065_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_RECLEGALDESC_V1.PDF DOCUMENTS VIEW
1_SITE_PLAN_V1.PDF DOCUMENTS VIEW
PDSD_OWNER_BUILDER_AFFIDAVIT_V1.PDF DOCUMENTS VIEW