Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/19/2023
Applicant:
Ramon VALDEZ
Description:
DUPLEX DUPLVAL82 T22-M0037

Permit Reviews

Permit Number - TC-MDP-0723-01233
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Start Date Submittal Complete Date Status  
09/19/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 09/26/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0723-01233
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Outstanding Activity Conditions - 1
Date Name
09/21/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0723-01233
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Date Description Comments
07/05/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0723-01233
Permite Description: DUPLEX DUPLVAL82 T22-M0037
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/09/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Partial Pass 11/9/23: revised plans required for 2 bedroom unit. Plan calls for 12AWG wire in bedroom 14awg installed. Ok to proceed.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0723-01233
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Completed Inspections - 19
Date Description Inspector Results Comments
10/13/2023 COT - RSPL - Rough Soil Passed
10/16/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Informed builder that future inspections would require paper plans.
10/16/2023 COT - RSBU - Preslab Passed Informed builder that future inspections would require paper plans.
10/16/2023 COT - RSEL - Grounding/Bonding Passed
11/06/2023 COT - RSBU - Firewall/Fire Barrier/Firestop Passed
11/06/2023 COT - RSBU - Interior Shear Bracing Passed n.a
11/06/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
11/06/2023 COT - RSBU - Roof Nailing Passed
11/09/2023 BULD - Electrical Clearance Passed 11/9/23: ECO TEP clearance for units 1 and 2
1/10/24 clearance resent
11/09/2023 COT - RSPL - Yard Water Line Passed
11/16/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
12/14/2023 COT - RSPL - Sewer Passed 12/14/23: passed
03/19/2024 COT - RSEL - Electrical Final Passed
03/19/2024 COT - RSEL - Outdoor Lighting Passed
03/19/2024 COT - RSME - Mechanical Final Passed
03/19/2024 COT - RSPL - Plumbing Final Passed
03/19/2024 RSBU - Building Final Passed
03/19/2024 RSBU - Building Progress Passed
03/19/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
5819 SITE PLAN_V1.PDF DOCUMENTS VIEW