Permit: TC-MDP-0625-00342
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
942 W 34TH ST
Address NEW:
942 W 34TH ST
Apply Date:
07/23/2025
Applicant:
Ramon VALDEZ
Description:
REV1: New lot sqft on all lots with new lot coverage Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Permit Reviews
Permit Number - TC-MDP-0625-00342
Permit Status: Inspections complete
Permit Description: REV1: New lot sqft on all lots with new lot coverage
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2026 | ADMINISTRATIVE v.2 | 01/09/2026 | APPROVED |
| 08/15/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 09/05/2025 | REQUIRES RESUBMIT |
| 10/28/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 11/12/2025 | APPROVED |
| 11/12/2025 | RESTAMP - RESIDENTIAL v.1 | 11/14/2025 | APPROVED |
| 01/09/2026 | SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.1 | 01/15/2026 | REQUIRES RESUBMIT |
| 12/10/2025 | ADMINISTRATIVE v.1 | 12/10/2025 | REQUIRES RESUBMIT |
| 07/24/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 08/11/2025 | REQUIRES RESUBMIT |
| 01/15/2026 | SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.2 | 01/16/2026 | APPROVED |
| 12/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/03/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0625-00342
Permit Status: Inspections complete
Permit Description: REV1: New lot sqft on all lots with new lot coverage
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 01/12/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 11/06/2025 | This project requires a Right-of-Way (ROW) permit issued by Department of Transportation and Mobility (DTM) prior to working in the public Right-of-Way. |
Conditions
Permit Number - TC-MDP-0625-00342
Permit Status: Inspections complete
Permit Description: REV1: New lot sqft on all lots with new lot coverage
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
| Date | Description | Comments |
|---|---|---|
| 06/16/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 06/16/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 08/07/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 12/04/2025 | A Minor Subdivision and Supplemental Site Plan for APN 11811043A, 11811043B, 11811044A, and 11811044B is required to be reviewed and approved by the City of Tucson prior to issuance of this building permit | |
| 01/08/2026 | A Minor Subdivision and Supplemental Site Plan for APN 11811043A, 11811043B, 11811044A, and 11811044B is required to be reviewed and approved by the City of Tucson prior to close out of this building permit |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0625-00342
Permite Description: REV1: New lot sqft on all lots with new lot coverage
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Partial Pass | 3-9-26: add shot pins & and anchor bolts at marked locations. Okay to continue with construction and will check for corrections at intermediates. |
| 05/01/2026 | COT - RSEL - Electrical Underground | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0625-00342
Permit Description: REV1: New lot sqft on all lots with new lot coverage
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/12/2026 | COT - RSPL - Rough Soil | Passed | 2.12.26 Approved |
|
| 02/12/2026 | COT - RSPL - Sewer | Passed | ||
| 02/18/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 2.18.26 Approved |
|
| 02/18/2026 | COT - RSBU - Preslab | Passed | 2.18.26 Approved |
|
| 03/09/2026 | COT - RSBU - Roof Nailing | Passed | 3-9-26: okay to dry-in roof. | |
| 03/11/2026 | BULD - Electrical Clearance | Passed | 3-11-26: okay to meter unit's 1&2. INCR clearance issued to TEP. | |
| 03/11/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3-11-26: intermediates approved. | |
| 03/11/2026 | COT - RSEL - Grounding/Bonding | Passed | 3-11-26: approved. | |
| 03/11/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 3-11-26: exterior clips/sheathing approved. | |
| 05/01/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | 05/01/2026 Verified firewall exterior 5/8" type-x was used and 8" on center screw schedule throughout. |
|
| 05/01/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 05/01/2026 | COT - RSEL - Electrical Final | Passed | ||
| 05/01/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 05/01/2026 | COT - RSME - Mechanical Final | Passed | ||
| 05/01/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 05/01/2026 | COT - RSPL - Yard Water Line | Passed | ||
| 05/01/2026 | RSBU - Building Final | Passed | ||
| 05/05/2026 | ENGR Engineering Final | Passed |