Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
07/18/2024
Applicant:
Brandon Kempel
Description:
SFR RKM45R T21-M0093 (REVISION Delta 4)

Permit Reviews

Permit Number - TC-MDP-0624-00741
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Start Date Submittal Complete Date Status  
07/22/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/30/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0624-00741
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Activity Conditions - 6
Date Name
06/24/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/30/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/30/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/30/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/30/2024 Post-Tension Inspection Report is required.
07/30/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0624-00741
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Date Description Comments
06/24/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00741
Permite Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
11/13/2024 COT - RSPL - Gas Pressure Test N/A Re-inspection required 11-13-24, pancake box overfilled at garage exterior lights. Box is rated for 6 cubic inches and contains 2 14/2 awg wires. Also, gas gauge at 7 psi and electrical panel not ready for temp power.
11/13/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 11-13-24, pancake box overfilled at garage exterior lights. Box is rated for 6 cubic inches and contains 2 14/2 awg wires. Also, gas gauge at 7 psi and electrical panel not ready for temp power.
11/20/2024 COT - BULD - SWG Clearance N/A Not Ready 11-20-24, not ready for gas connection l

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00741
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Completed Inspections - 21
Date Description Inspector Results Comments
09/09/2024 COT - RSPL - Yard Water Line Passed 9/9/24: Main water line is connected to city meter and under street pressure with no leaks. Okay to shade pipe and backfill trench.
09/09/2024 COT - RSPL - Sewer Passed 9/9/24: Underground plumbing is installed and connected to main sewer system with green tracer wire in place, entire system under water test. Okay to shade pipes and backfill trenches.
09/09/2024 COT - RSPL - Rough Soil Passed 9/9/24: Underground plumbing is installed and connected to main sewer system with green tracer wire in place, entire system under water test. Okay to shade pipes and backfill trenches.
09/16/2024 COT - RSEL - Electrical Underground Passed
09/17/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 9/17/2024. Okay for concrete placement.
09/17/2024 COT - RSBU - Preslab Passed 9/17/2024. Okay for concrete placement.
09/17/2024 COT - RSEL - Grounding/Bonding Passed
10/07/2024 COT - RSBU - Roof Nailing Passed Okay to proceed with rough-in.
10/07/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Okay to proceed with rough-in.
11/19/2024 COT - RSPL - Gas Pressure Test Passed 11-19-24, verified gas pressure test at 15 psi
11/22/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 11-22-24, residential intermediate approved. Okay to continue with construction.
11/29/2024 BULD - Electrical Clearance Passed 11-29-24, panel approved to be energized (ECO).
12/10/2024 COT - RSBU - Interior Shear Bracing Passed 12-10-24, interior shear bracing verified as per approved plans prior. Okay to tape & texture drywall.
02/06/2025 COT - BULD - SWG Clearance Passed 2/6/25 passed SWG CLEARANCE
02/12/2025 COT - RSEL - Electrical Final Passed Passed final 2/12/25 CLEARANCE ECO
02/12/2025 COT - RSEL - Outdoor Lighting Passed Passed final 2/12/25
02/12/2025 COT - RSME - Mechanical Final Passed Passed final 2/12/25
02/12/2025 COT - RSPL - Plumbing Final Passed Passed final 2/12/25
02/11/2025 ENGR Engineering Final Passed
02/12/2025 RSBU - Building Final Passed Passed final 2/12/25
02/12/2025 RSBU - Building Progress Passed Passed final 2/12/25

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT.-2024-07-18_V1.PDF DOCUMENTS VIEW